Final | 6/20/2014 | 6/20/2014 | 6/20/2014 | P | PASS |
Chad Schwendiman
|
|
|
if questions call Mark @ ###-#### or Matt @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
Final | 5/14/2014 | 5/14/2014 | 5/14/2014 | P | PART |
Alan Hauser
|
|
|
|
Pressure Test | 5/9/2014 | 5/9/2014 | 5/9/2014 | P | PASS |
Alan Hauser
|
|
|
5# on flue
|
Pressure Test | 4/22/2014 | 4/23/2014 | 4/23/2014 | A | PASS |
Dixie Fellows
|
|
|
if questions call Matt @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann..all hydronics on north side of space ok at 100lb test
|
Pressure Test | 4/21/2014 | 4/21/2014 | 4/21/2014 | P | PART |
Dixie Fellows
|
|
|
if questions call Matt @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann..2--100lb tests on south side ok
|
Mec-Aging Inspection | 3/18/2014 | 3/18/2014 | 3/18/2014 | | CANC |
Alan Hauser
|
|
|
|
Final | 12/17/2013 | 12/18/2013 | 12/18/2013 | A | PART |
Troy James
|
|
|
Questions call Mark ###-#### >> Inspection requested via web by Stacia Haumann ok phase 2B
|
Rough-in | 11/19/2013 | 11/20/2013 | 11/20/2013 | A | PASS |
Alan Hauser
|
|
|
call ###-#### to meet you
|
Rough-in | 11/18/2013 | 11/19/2013 | 11/19/2013 | A | PEND |
Dixie Fellows
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann...rescheduled for wed am with alan h
|
Pressure Test | 11/1/2013 | 11/1/2013 | 11/1/2013 | P | PASS |
Alan Hauser
|
|
|
fan coil hook up piping ok
|
Final | 9/9/2013 | 9/10/2013 | 9/10/2013 | A | PART |
Alan Hauser
|
|
|
Final for Phase 2A only. please call Mark BEFORE arrival to job site ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|
Rough-in | 6/27/2013 | 6/28/2013 | 6/28/2013 | A | PART |
Alan Hauser
|
|
|
hydronic test ok for piping to roof
|
Pressure Test | 5/21/2013 | 5/22/2013 | 5/22/2013 | A | PART |
Alan Hauser
|
|
|
test ok for hydronic loop and chilled water
|
Final | 2/25/2013 | 2/26/2013 | 2/26/2013 | A | PART |
Jim Johnson
|
|
|
this is a Final for PHASE 1 ONLY, there will be other phases being called in on this permit at a later date. so please dont close it out. please call Mark 30 mins prior to arrival, he will need to walk you through the job site ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann phase 1 final ok
|
Rough-in | 1/29/2013 | 1/30/2013 | 1/30/2013 | A | PART |
Alan Hauser
|
|
|
|
Rough-in | 12/26/2012 | 12/26/2012 | 12/26/2012 | A | PART |
Alan Hauser
|
|
|
steam pipes over existing e.r. ok
|
Rough-in | 12/21/2012 | 12/26/2012 | 12/26/2012 | A | CANC |
Alan Hauser
|
|
|
if questions call Mark @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann
|