Final | 9/5/2013 | 9/6/2013 | 9/6/2013 | A | PASS |
Eric Strole
|
|
|
>> Inspection requested via web by Konrad Swartz
|
Rough-in | 7/31/2013 | 8/1/2013 | 8/1/2013 | A | PASS |
Eric Strole
|
|
|
Rough in mechanical with gas pressure. The city plans are on site in the tray on the side of the furnace. Phone #: ###-#### >> Inspection requested via web by Konrad Swartz-20 lb gas test and rough-in pass.
|
Final | 7/31/2013 | 8/1/2013 | 7/31/2013 | A | CANC |
Eric Strole
|
|
|
The city plans are on site in the tray on the side of the furnace. Phone #: ###-#### >> Inspection requested via web by Konrad Swartz Inspection cancelled from web by: Konrad Swartz
|
Rough-in | 7/31/2013 | 8/1/2013 | 7/31/2013 | A | CANC |
Eric Strole
|
|
|
Rough in mechanical with gas pressure.
The city plans are on site in the tray on the side of the furnace. Phone #: ###-#### >> Inspection requested via web by Konrad Swartz Inspection cancelled from web by: Konrad Swartz
|
Rough-in | 7/29/2013 | 7/30/2013 | 7/30/2013 | A | FAIL |
Eric Strole
|
|
|
Rough in mechanical with gas pressure Phone #: ###-#### >> Inspection requested via web by Konrad Swartz-need to complete rough-in and have approved manual-j on site for inspection.
|