Final | 9/3/2013 | 9/5/2013 | 9/5/2013 | A | PASS |
Alan Hauser
|
|
|
|
Final | 8/20/2013 | 8/21/2013 | 8/21/2013 | A | PART |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by April Thomas need co2 alarem,s for final contractor to recall when ready
|
Pressure Test | 8/20/2013 | 8/21/2013 | 8/21/2013 | A | PASS |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by April Thomas 20 # pressure test ok
|
Pressure Test | 8/20/2013 | 8/20/2013 | 8/20/2013 | P | NR |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by April Thomas not ready contractor to recall when ready
|
Final | 8/20/2013 | 8/20/2013 | 8/20/2013 | P | NR |
Jim Johnson
|
|
|
Phone #: ###-#### >> Inspection requested via web by April Thomas not ready contractor to recall when ready
|