Final | 7/24/2014 | 7/24/2014 | 7/24/2014 | P | PASS |
Chad Schwendiman
|
|
|
|
Conference | 10/31/2013 | 11/1/2013 | 11/1/2013 | A | PASS |
Bill VanDegrift
|
|
|
Final mechanical Phone #: ###-#### >> Inspection requested via web by Konrad Swartz final ok
|
Final | 10/30/2013 | 10/31/2013 | 10/30/2013 | P | CANC |
Eric Strole
|
|
|
Final with fireplace Phone #: ###-#### >> Inspection requested via web by Konrad Swartz Inspection cancelled from web by: Konrad Swartz
|
Rough-in | 9/26/2013 | 9/26/2013 | 9/26/2013 | P | PASS |
Alan Hauser
|
|
|
20# ok, no duct blast done
|
Rough-in | 9/24/2013 | 9/24/2013 | 9/24/2013 | P | FAIL |
Eric Strole
|
|
|
Rough in mech w/ gas pressure >> Inspection requested via web by Konrad Swartz-20 lb gas test pass. Need to complete crawl for rough-in inspection.
|