Final | 12/8/2014 | 12/8/2014 | 12/8/2014 | P | PASS |
Alan Hauser
|
|
|
|
Rough-in | 10/9/2014 | 10/9/2014 | 10/9/2014 | P | PASS |
Alan Hauser
|
|
|
RI above ceiling for cover in Area A. Contact Mario ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Rough-in | 9/29/2014 | 9/30/2014 | 9/30/2014 | A | PART |
Alan Hauser
|
|
|
Need a Final for the Sterile Storage area. this area ok for final
|
Rough-in | 9/25/2014 | 9/26/2014 | 9/26/2014 | A | PASS |
Alan Hauser
|
|
|
Rough in for Sterile Storage. contact Stan ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Rough-in | 9/3/2014 | 9/4/2014 | 9/4/2014 | A | PASS |
Alan Hauser
|
|
|
Treasure Valley Hospital Lobby RI so ceiling tile can go in. Contact Stan ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Rough-in | 8/18/2014 | 8/19/2014 | 8/19/2014 | A | PASS |
Alan Hauser
|
|
|
Final inspection for the Locker Room area ok
|
Rough-in | 8/14/2014 | 8/14/2014 | 8/14/2014 | P | PASS |
Alan Hauser
|
|
|
Rough in for cover in Locker rooms. ok for cover
|
Final | 8/11/2014 | 8/12/2014 | 8/12/2014 | A | PART |
Alan Hauser
|
|
|
Stan w/TML, PACU area ok for cover and final
|
Rough-in | 7/28/2014 | 7/28/2014 | 7/28/2014 | P | PASS |
Alan Hauser
|
|
|
RI for cover area 2A RI area 2C Contact Mario ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Rough-in | 7/15/2014 | 7/16/2014 | 7/16/2014 | A | PASS |
Alan Hauser
|
|
|
RI for phase 2A PACU Contact Mario ###-####
|
Rough-in | 6/20/2014 | 6/23/2014 | 6/23/2014 | A | PASS |
Chad Schwendiman
|
|
|
Ri fir phase 2-b Lobby for cover. Contact mario ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty - Phase 2-b lobby approved for cover.
|
Rough-in | 5/29/2014 | 5/30/2014 | 5/30/2014 | A | PART |
Alan Hauser
|
|
|
Mario w/TML Phase 2B,cover inspection, ok for tile
|
Rough-in | 5/12/2014 | 5/12/2014 | 5/12/2014 | P | PART |
Alan Hauser
|
|
|
Mario w/TML. Area Lobby Phase 2A, duct sealed and ready for wrap
|
Rough-in | 4/14/2014 | 4/15/2014 | 4/15/2014 | A | PART |
Alan Hauser
|
|
|
Inspect for Occupancy of OR Addition, Pre Op & Dinning. ok for occupancy
|
Rough-in | 4/4/2014 | 4/7/2014 | 4/7/2014 | A | PART |
Chad Schwendiman
|
|
|
Rough in for cover. Contact Mario ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty - Area c OR addition ok to cover, 1C Reno. rough -in okay.
|
Rough-in | 3/27/2014 | 3/28/2014 | 3/28/2014 | P | PART |
Troy James
|
|
|
Contact Mario ###-#### RI for cover area A & B OR''s. Phone #: ###-#### >> Inspection requested via web by Dan Flaherty ok ceiling tile at west side onlly
|
Rough-in | 3/14/2014 | 3/17/2014 | 3/17/2014 | A | PART |
Alan Hauser
|
|
|
operating rooms ok for cover
|
Rough-in | 3/13/2014 | 3/14/2014 | 3/14/2014 | A | CANC |
Troy James
|
|
|
Rough in for OR rooms. Contact Mario ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty rescheduled for alan on monday
|
Final | 3/13/2014 | 3/13/2014 | 3/13/2014 | A | PART |
Alan Hauser
|
|
|
area e
|
Rough-in | 3/7/2014 | 3/10/2014 | 3/10/2014 | P | PART |
Alan Hauser
|
|
|
duct ok
|
Rough-in | 2/13/2014 | 2/14/2014 | 2/14/2014 | A | PART |
Alan Hauser
|
|
|
duct ok and sealed in O. R.areas, ok to insulate and ok for tile in patient addition
|
Rough-in | 1/14/2014 | 1/14/2014 | 1/14/2014 | P | PART |
Alan Hauser
|
|
|
final occ. for phase 1b
|
Rough-in | 1/13/2014 | 1/14/2014 | 1/14/2014 | A | PART |
Alan Hauser
|
|
|
Need Occupancy for 1st phase. occupancy ok
|
Rough-in | 12/20/2013 | 12/20/2013 | 12/20/2013 | P | PART |
Alan Hauser
|
|
|
Final for phase 1A. Contact Mario ###-#### Phone #: ###-#### >> Inspection requested via web by Dan Flaherty
|
Rough-in | 11/7/2013 | 11/8/2013 | 11/8/2013 | A | PART |
Alan Hauser
|
|
|
Rough in for 1st phase Contact Mario ###-#### Phone #: ###-#### hvac ok for areas highlighted and signed on city plans
|