Final | 6/7/2016 | 6/7/2016 | 6/7/2016 | P | PASS |
Troy James
|
|
|
Mec Final, 5th Floor, Party Room. Any additional questions please contact Shane Stowe @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann
|
Mec-Aging Inspection | 4/1/2016 | 4/1/2016 | 4/1/2016 | | PEND |
Troy James
|
|
|
bbq will be installed end of month and fireplace next week. Contractor will call when completed.
|
Mec-Aging Inspection | 1/1/2016 | 1/1/2016 | 1/4/2016 | | PEND |
Troy James
|
|
|
wip
|
Pressure Test | 10/2/2015 | 10/5/2015 | 10/5/2015 | A | PASS |
Troy James
|
|
|
5TH FLOOR. IF QUESTIONS CALL SHANE @ ###-#### Phone #: ###-#### Inspection requested via web by Stacia Haumann test gas line at makers studio and heaters at parking garage
|
Pressure Test | 8/28/2015 | 8/28/2015 | 8/28/2015 | P | PASS |
Troy James
|
|
|
LOCATED here @ DEBEST PLUMBING WELDING SHOP - 11477 W. President Drive Boise, ID 83713. Call Hollie @ ###-#### when you arrive and she will take you back to where the gas piping is under pressure test. (this piping is for JUMP, just needs to be tested before being sent over to job site). Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ok gas line in columns
|
Rough-in | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | PASS |
Troy James
|
|
|
mechanical gas test. if questions call Shane @ ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ok gasline at 6th floor kitchen, 1st floor fireplace and gas line test at generator and 2nd floor
|
Pressure Test | 6/23/2015 | 6/24/2015 | 6/24/2015 | A | PART |
Troy James
|
|
|
if questions call Shane @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ok pressure test gas line to water heaters 6th floor
|
Pressure Test | 3/25/2015 | 3/25/2015 | 3/25/2015 | P | PART |
Troy James
|
|
|
if questions please call Shane ###-####. Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ok gas supply header to kitchen and water heater room 6th floor
|
Pressure Test | 10/30/2014 | 10/31/2014 | 10/31/2014 | A | PASS |
Troy James
|
|
|
if questions call Shane @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann Ok main gas line to meter for gas tag at 60#. Partia gas inspection approval.
|
Pressure Test | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Troy James
|
|
|
Hydronic. if questions call Shane @ ###-####. Phone #: ###-#### Inspection requested via web by Stacia Haumann ok hydronics at 5th floor jump room and makers studio
|
Pressure Test | 9/11/2014 | 9/12/2014 | 9/16/2014 | A | PASS |
Troy James
|
|
|
Pressure test only, early afternoon please. Thanks. Phone #: ###-#### >> Inspection requested via web by April Thomas gas line from meter to range 20# test
|
Pressure Test | 8/21/2014 | 8/21/2014 | 8/22/2014 | P | PASS |
Troy James
|
|
|
if questions call Shane @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ok gas test from mens restroom 4 th floor to sprinkler room
|
Pressure Test | 6/12/2014 | 6/12/2014 | 6/12/2014 | P | PASS |
Troy James
|
|
|
if questions call Shane @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ok hydronics to vav boxes at 1st and 2nd floors pioneer room and ok at media room
|
Pressure Test | 6/4/2014 | 6/5/2014 | 6/5/2014 | A | PASS |
Troy James
|
|
|
Hydro Static test - if questions call Shane @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann ok test from basement shaft to s/w side wall and then from super column to air handler at mezz above studio room
|
Pressure Test | 5/27/2014 | 5/28/2014 | 5/28/2014 | P | PART |
Bill VanDegrift
|
|
|
if questions call Shane @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann 20# test 2nd floor water heater room to units ok
|
Rough-in | 12/18/2013 | 12/19/2013 | 12/19/2013 | A | PART |
Bill VanDegrift
|
|
|
hydronics. if questions call Shane @ ###-#### Phone #: ###-#### >> Inspection requested via web by Stacia Haumann 100 psi on 4-1 1/2" risers at super colum- stairs
|