Final | 5/29/2014 | 5/29/2014 | 5/29/2014 | P | PASS |
Dixie Fellows
|
|
|
Derrick Phone #: ###-####
|
Final | 5/13/2014 | 5/14/2014 | 5/14/2014 | A | PART |
Dixie Fellows
|
|
|
PIPES HAVE BEEN INSULATED. CALL SAM IF ANY QUESTIONS ###-#### >> Inspection requested via web by Tobi Wilson--Waiting for final values on brewing equipment per Dixie
|
Final | 5/9/2014 | 5/12/2014 | 5/12/2014 | A | PART |
Dixie Fellows
|
|
|
THIS IS FINAL ON GLYCOL. IF ANY QUESTIONS, CALL TOBI WILSON ###-#### >> Inspection requested via web by Tobi Wilson..waiting on info from structural engineer..this permit is ready for final
|
Pressure Test | 4/28/2014 | 4/29/2014 | 4/29/2014 | A | PASS |
Dixie Fellows
|
|
|
PLEASE CALL SAM COLLIER IF YOU CANNOT DO THIS PRESSURE TEST AM ON 4/29. THANK YOU..60LB TEST TO ALL EQUIPMENT OK CELL: ###-#### >> Inspection requested via web by Tobi Wilson
|
Final | 4/28/2014 | 4/28/2014 | 4/28/2014 | P | FAIL |
Dixie Fellows
|
|
|
contact sam for info..NEED TO DISCONNECT GAS TO ALL EQUIPMENT AND TEST IT..THE ONLY INSPECTION DONE TO THIS POINT WAS FROM THE METER TO THE MEZANINE..READ PLANS FOR MANUF REQUIREMENTS TO CONNECT GAS TO EQUIPMENT
|
Pressure Test | 2/18/2014 | 2/18/2014 | 2/18/2014 | P | PART |
Dixie Fellows
|
|
|
Sam Phone #: ###-####..60lb test from meter to mezanine ok..will need to test drops to all equipment
|
Pressure Test | 2/12/2014 | 2/12/2014 | 2/12/2014 | P | CANC |
Dixie Fellows
|
|
|
Ima Phone #: ###-####...NO ACCESS TO GUAGE
|