Final | 5/28/2014 | 5/28/2014 | 5/28/2014 | P | PASS |
Dixie Fellows
|
|
|
Dixie this is for the final value on the Chiller see Rita if you have questions..OK TO SIGN THE CARD
|
Final | 5/19/2014 | 5/20/2014 | 5/20/2014 | A | PART |
Dixie Fellows
|
|
|
Phone #: ###-#### >> Inspection requested via web by Karl Hestekin..waiting for final equipment value..brewing tanks,boiler,chiller..etc
|
Final | 5/12/2014 | 5/12/2014 | 5/12/2014 | P | NR |
Dixie Fellows
|
|
|
Phone #: ###-#### >> Inspection requested via web by Karl Hestekin..WAITING ON STRUCTURAL ENGINEERING ON ROOF
|
Final | 5/8/2014 | 5/8/2014 | 5/8/2014 | P | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### >> Inspection requested via web by Karl Hestekin - NEED TO ADD WALL SUPPORTS TO THE VERTICAL SECTION OF STAINLESS STEEL VENT PIPE. NEED TO ADD SUPPORTS TO THE VENT PIPES ON THE ROOF. tHERE IS A NEW CHILLER IMSTALLED ON PRESSURE TREATED RED WOOD ON THE ROOF, CHILLER WAS SUPPLIED BY GENRAL INSTALLED ON THE ROOF BY KMD MECH. DO NOT KNOW IF THIS WAS STRUCTRALY ENGINEERED FOR THE WIEGHT. THE OWNER SAID THE REFRIGIRATION PIPPING WAS DONE BY THE PLUMBER. I CAN;T FIND A PERMIT FOR OT. I TOLD THE OWNER IT NEEDS TO BE PERMITED. NONE OF THE PIPPING WAS INSULATED.
|
Final | 4/29/2014 | 4/29/2014 | 4/29/2014 | P | NR |
Dixie Fellows
|
|
|
Re-inspection For Bogus Brewery Phone #: ###-#### >> Inspection requested via web by Karl Hestekin..WAITING ON INFO FROM ENGINEER FOR THE FLUE ON BOILER
|
Final | 4/28/2014 | 4/28/2014 | 4/28/2014 | P | FAIL |
Dixie Fellows
|
|
|
Phone #: ###-#### >> Inspection requested via web by Karl Hestekin..need manuf specs for venting on equipment
|
Rough-in | 2/11/2014 | 2/12/2014 | 2/12/2014 | A | PART |
Dixie Fellows
|
|
|
Phone #: ###-#### >> Inspection requested via web by Karl Hestekin..ductwork for rtu ok
|