Final | 9/25/2015 | 9/25/2015 | 9/25/2015 | A | PASS |
Chad Schwendiman
|
|
|
Contact Jake ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty
|
Rough-in | 9/10/2015 | 9/11/2015 | 9/11/2015 | A | PASS |
Chad Schwendiman
|
|
|
Jake/###-####/ ceiling cover inspection for the entire 3rd floor Phone #: ###-#### Inspection requested via web by Crystal Grant
|
Rough-in | 8/18/2015 | 8/19/2015 | 8/19/2015 | P | PART |
Chad Schwendiman
|
|
|
Rough in for cover on 3rd floor bathrooms. Contact Jake ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - okay to cover bathroom ceilings
|
Rough-in | 8/17/2015 | 8/18/2015 | 8/18/2015 | A | PART |
Chad Schwendiman
|
|
|
Rough in for cover 3rd floor shafts. Contact Jake ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - 3rd floor shaft okay
|
Rough-in | 7/23/2015 | 7/23/2015 | 7/23/2015 | P | PART |
Alan Hauser
|
|
|
fire dampers ok at 1-2 ceiling/floor and 2-3 ceiling/floor
|
Rough-in | 5/29/2015 | 6/1/2015 | 6/1/2015 | A | PART |
Chad Schwendiman
|
|
|
Request for Temp Occupancy. I understand that Boise City has approved this with the Fire alarm plans been submitted. Contact is Coly with Jordan Wilcomb ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - this was a partial final, I entered a partial final for it.
|
Final | 6/1/2015 | 6/1/2015 | 6/1/2015 | A | PART |
Chad Schwendiman
|
|
|
Request for Temp Occupancy. I understand that Boise City has approved this with the Fire alarm plans been submitted. Contact is Coly with Jordan Wilcomb ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - 1st and 2nd floor okay. Signed temporary occupancy.
|
Rough-in | 5/28/2015 | 5/29/2015 | 5/29/2015 | A | FAIL |
Chad Schwendiman
|
|
|
Request for Temp Occupancy for 1st ; 2nd floors. Contact Colyn with Jordan Wilcomb ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - waiting for fire alarm drawings to be resubmitted showing smoke detection for HVAC system
|
Rough-in | 4/28/2015 | 4/29/2015 | 4/29/2015 | A | PASS |
Chad Schwendiman
|
|
|
1st floor RI for cover. Contact Jake ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - okay to cover ceing on the 1st floor
|
Rough-in | 4/24/2015 | 4/24/2015 | 4/24/2015 | A | PART |
Alan Hauser
|
|
|
ok for tile around diffusers on 2nd floor
|
Rough-in | 4/20/2015 | 4/20/2015 | 4/20/2015 | P | PASS |
Chad Schwendiman
|
|
|
Rough in for 1st ; 2nd floor. Contact Jake ###-#### Phone #: ###-#### Inspection requested via web by Dan Flaherty - 1st and 2nd floors
|
Rough-in | 3/10/2015 | 3/10/2015 | 3/10/2015 | A | PART |
Alan Hauser
|
|
|
1st floor bathrooms & 2nd fl bathrooms ok for cover, and 1st floor duct sealed and ready for insulation
|