Conference | 11/15/2016 | 11/15/2016 | 11/15/2016 | P | PASS |
Chad Schwendiman
|
|
|
Inspection of rerouting of vent to the roof of block 22 building, per code alternate. Passed inspections per Chad.
|
Final | 10/20/2016 | 10/20/2016 | 10/20/2016 | P | PASS |
Chad Schwendiman
|
|
|
VRT, Clearwater and District Building, final mechanical reinspection. Please contact Rob Bulter. Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Final | 10/17/2016 | 10/18/2016 | 10/18/2016 | A | FAIL |
Chad Schwendiman
|
|
|
Clearwater 9-Story, District and VRT Shell ; Core final mechanical inspection. Please contact Rob Butler. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Need to cap future grease duct in the 1st floor T.I. Need to wrap future grease duct in 1st floor T.I. Need to protect shaft penetration per listing on fire wrap.
|
Final | 10/7/2016 | 10/10/2016 | 10/10/2016 | A | PART |
Chad Schwendiman
|
|
|
Final inspection for VRT, including boiler flue rework. All documents will be emailed to Chad S. Phone #: ###-#### Inspection requested via web by Melissa Kaae - temporary occupancy of the VRT space okay
|
Conference | 10/4/2016 | 10/5/2016 | 10/5/2016 | A | DONE |
Chad Schwendiman
|
|
|
Please contact Pat Nichols to discuss plan for VRT boiler flue issues. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Met with RM and discussed venting. Need documentation from boiler manufacure's engineering department showing changes from original installation instructions
|
Final | 9/28/2016 | 9/29/2016 | 9/29/2016 | A | PART |
Chad Schwendiman
|
|
|
Partial final inspection for VRT. Would like to schedule this for late morning inspection, please contact Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Limited temporary occupancy okay for bus training. The boilers will not be used during this time frame.
|
Final | 9/27/2016 | 9/28/2016 | 9/28/2016 | P | FAIL |
Chad Schwendiman
|
|
|
Partial final inspection for temporary occupancy in VRT (all expect boiler flue). TAB report will be emailed to Chad S. Please contact Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - I received the air balance report for the vrt space and the co exhaust system, but the condensate piping is still not complete.
|
Rough-in | 9/22/2016 | 9/23/2016 | 9/23/2016 | A | PART |
Chad Schwendiman
|
|
|
Call Jim Brown - 1st Floor - Trash Chute Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover exhaust duct in 1st floor to trash shoot
|
Final | 9/21/2016 | 9/21/2016 | 9/21/2016 | P | PART |
Chad Schwendiman
|
|
|
Partial Final inspection for 1st Floor and 2nd Floor Prefunction/Lobby Areas, please contact Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - temporary occupancy okay for the 1st and 2nd floor lobby
|
Final | 9/16/2016 | 9/16/2016 | 9/16/2016 | P | PART |
Chad Schwendiman
|
|
|
Partial Final inspection, 4th Floor District Building, please contact Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - temp occupancy okay for the gbad side of the building.
|
Final | 9/15/2016 | 9/16/2016 | 9/16/2016 | P | CANC |
Chad Schwendiman
|
|
|
Partial Final inspection for District Building, for Temporary Occupancy, please contact Jim Brown. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Inspection cancelled from web by: Melissa Kaae
|
Rough-in | 9/12/2016 | 9/13/2016 | 9/13/2016 | P | PART |
Chad Schwendiman
|
|
|
GBAD rough-in cover: 1st floor lobby ; vestibule. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover hard lid portion of 1st floor lobby gbad side
|
Conference | 9/13/2016 | 9/13/2016 | 9/13/2016 | P | CANC |
Chad Schwendiman
|
|
|
1:30
|
Final | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PART |
Chad Schwendiman
|
|
|
Partial final - Clearwater 4th floor. Balance report will be emailed to Chad S. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - temporary occupancy okay for the clearwater side of the 4th floor
|
Rough-in | 8/30/2016 | 8/31/2016 | 8/31/2016 | A | PART |
Chad Schwendiman
|
|
|
GBAD - Insulation cover for 1st floor ; 2nd floor lobby areas. Onsite contact: Rob Butler. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to insulate
|
Rough-in | 8/26/2016 | 8/26/2016 | 8/26/2016 | P | FAIL |
Chad Schwendiman
|
|
|
VRT rough-in cover. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Need venting instructions for boilers
|
Rough-in | 8/17/2016 | 8/18/2016 | 8/18/2016 | A | PART |
Chad Schwendiman
|
|
|
Rough-in cover for GBAD 4th floor ballroom ceiling space. Onsite contact: Rob Butler. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 4th floor bathromms in gbad okay to cover. ballroom okay
|
Rough-in | 8/16/2016 | 8/17/2016 | 8/17/2016 | A | PART |
Chad Schwendiman
|
|
|
Late AM inspection if possible. GBAD fire wrap. Onsite contact: Rob Butler. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer fire wrap okay on grease duct, fire wrap okay on vertical relief duct
|
Rough-in | 8/11/2016 | 8/11/2016 | 8/11/2016 | P | PART |
Chad Schwendiman
|
|
|
Cover for VRT bathrooms. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover the 2 single bathrooms in the basement for VRT
|
Final | 8/9/2016 | 8/10/2016 | 8/10/2016 | A | PART |
Chad Schwendiman
|
|
|
Partial final for 5th, 9th, ; 10th floors. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - temporary occupancy okay for 5th floor, 9th floor, and 10th floor core and shell area's.
|
Rough-in | 8/8/2016 | 8/9/2016 | 8/9/2016 | A | PART |
Chad Schwendiman
|
|
|
1st layer fire wrap on 4th floor. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae- 1st floor fire wrap okay on grease duct between shaft and roof
|
Rough-in | 8/5/2016 | 8/8/2016 | 8/8/2016 | A | PEND |
Chad Schwendiman
|
|
|
Cover for VRT restrooms. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae This should have been a confrence. - walked parking garage area to look at ductwork. Need to check what walls are fire walls and if any dampers are required.
|
Rough-in | 8/4/2016 | 8/5/2016 | 8/5/2016 | A | PART |
Chad Schwendiman
|
|
|
Early AM grease duct light test 4th floor. Approved by Bill VanDegrift ; Chad Schwendiman. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae -grease duct light test pass on 4th floor from shaft up to roof curbs of gbad
|
Final | 7/29/2016 | 7/29/2016 | 7/29/2016 | P | PART |
Bill VanDegrift
|
|
|
Partial final mechanical inspection for temporary occupancy for clearwater. temp occ ok 7th floor, elevator lobby floor 1,3,5,6,7,8. stairwell pressureization floors 1 through 9.
|
Final | 7/28/2016 | 7/29/2016 | 7/29/2016 | A | FAIL |
Chad Schwendiman
|
|
|
Partial final mechanical inspection for temporary occupancy of the 1st floor lobby, elevator lobby, 6th floor, and 7th floor. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - still need documintation on muffler for generator, dampers missing power on 8thy floor.
|
Rough-in | 7/27/2016 | 7/29/2016 | 7/29/2016 | A | PART |
Chad Schwendiman
|
|
|
1st floor, stair 2 corridor. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Okay to cover ceiling in 1st floor exit
|
Rough-in | 7/27/2016 | 7/28/2016 | 7/28/2016 | P | PART |
Chad Schwendiman
|
|
|
Shaft fire damper inspection. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover shaft in gbad on 4th floor
|
Final | 7/27/2016 | 7/28/2016 | 7/28/2016 | A | FAIL |
Chad Schwendiman
|
|
|
Partial final mechanical inspection for temporary occupancy of the 1st floor lobby, elevator lobby, 6th floor, and 7th floor. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - need generator muffler installation instructions, need 8th floor elevator lobby report.
|
Rough-in | 7/26/2016 | 7/26/2016 | 7/26/2016 | P | PASS |
Ben Livingston
|
|
|
1st floor rough-in cover ; 2nd layer grease wrap. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae- 1st floor lobby ok to cover, 2nd layer fire wrap ok
|
Rough-in | 7/21/2016 | 7/22/2016 | 7/22/2016 | P | PART |
Chad Schwendiman
|
|
|
Second Layer Fire Wrap Inspection - 7-22-16 - PM GBAD Building RM Mechanical contact person is Jim Brown.
Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer pass on grease duct 90's and duct extending out of the top of the shaft
|
Rough-in | 7/21/2016 | 7/22/2016 | 7/22/2016 | A | PART |
Chad Schwendiman
|
|
|
The explanation for requesting an after-hours inspection is that we are asking for a light test on a grease duct. RM Mechanical contact person is Jim Brown.
Phone #: ###-#### Inspection requested via web by Melissa Kaae - Light test pass on 1st floor of GBAD where duct extends out of the shaft
|
Rough-in | 7/18/2016 | 7/20/2016 | 7/20/2016 | P | PASS |
Ben Livingston
|
|
|
Will you please make this the last inspection of the day? 1st layer fire wrap inspection. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae- 1st layer out of shaft ok
|
Rough-in | 7/20/2016 | 7/21/2016 | 7/20/2016 | A | PASS |
Ben Livingston
|
|
|
4th floor bathrooms. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae- ok to cover
|
Conference | 7/12/2016 | 7/20/2016 | 7/20/2016 | A | CANC |
Chad Schwendiman
|
|
|
Meet with RM at 8:00 in the 1st floor lobby to discuss temparary occupancy
|
Rough-in | 7/18/2016 | 7/20/2016 | 7/20/2016 | A | PART |
Chad Schwendiman
|
|
|
Early AM light test inspection. Approved by Bill V. ; Chad S. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - grease duct light test pass on 90's at top of shaft in GBAD
|
Rough-in | 7/13/2016 | 7/14/2016 | 7/14/2016 | P | PASS |
Chad Schwendiman
|
|
|
Second Layer Fire Wrap, 1st Floor, Thursday PM, Jim Brown is contact Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Rough-in | 7/13/2016 | 7/13/2016 | 7/13/2016 | P | PART |
Chad Schwendiman
|
|
|
Rough-in cover inspection, 1st Floor CCD 036 bathrooms, Today PM, Jim Brown is contact
Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to insulate supply duct in 4th floor gbad building, okay to cover ceilings in 1st floor bathrooms for ti space on west side
|
Conference | 7/13/2016 | 7/13/2016 | 7/13/2016 | A | DONE |
Chad Schwendiman
|
|
|
Meet with RM at 8:00 in 1st floor lobby to discuss temp occupancy
|
Conference | 7/13/2016 | 7/14/2016 | 7/13/2016 | P | CANC |
Chad Schwendiman
|
|
|
Second Layer Fire Wrap, 1st Floor, Thursday PM, Jim Brown is contact
Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Inspection cancelled from web by: Melissa Kaae
|
Rough-in | 7/11/2016 | 7/11/2016 | 7/11/2016 | P | PART |
Chad Schwendiman
|
|
|
FIRST FLOOR - FIRST LAYER - GREASE DUCT FIRE WRAP CALL JIM BROWN Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer pass
|
Rough-in | 7/8/2016 | 7/11/2016 | 7/11/2016 | A | PART |
Chad Schwendiman
|
|
|
1ST FLOOR - CORE BATHROOM INSPECTION CALL JIM BROWN Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st floor bathrooms ok to cover
|
Rough-in | 7/6/2016 | 7/7/2016 | 7/7/2016 | A | PART |
Chad Schwendiman
|
|
|
EARLY AM - (6:00 AM) GREASE DUCT LIGHT INSPECTION • RM Mechanical contact person is Jim Brown. His cell phone is ###-####. A backup contact is Roger Elam and his cell is ###-####. • RM Mechanical agrees to pay for a minimum of two hours of time from the inspector that will be calculated on OT basis Phone #: ###-#### Inspection requested via web by Melissa Kaae - Grease duct light test pass on the 1st floor from the shaft to the ti on the west side. , Grease duct light test pass on the 1st floor from the elevator lobby out to the open area in the north east corner of the building
|
Rough-in | 6/27/2016 | 6/27/2016 | 6/27/2016 | P | PASS |
Ben Livingston
|
|
|
1ST FLOOR - 2ND LAYER INSULATION GREASE DUCT INSPECTION CALL JIM BROWN. Phone #: ###-#### Inspection requested via web by Melissa Kaae- 2nd layer on elbow and duct through wall ok
|
Rough-in | 6/24/2016 | 6/24/2016 | 6/24/2016 | P | PASS |
Ben Livingston
|
|
|
Fire access lobby, 1st layer fire wrap. Onsite contact: Jim Brown Phone #: ###-#### Inspection requested via web by Melissa Kaae1st layer ok
|
Rough-in | 6/23/2016 | 6/24/2016 | 6/24/2016 | A | PASS |
Ben Livingston
|
|
|
2 Inspection Items Requested: 1) 1st Floor - Grease Duct - Fire Access Lobby - Light Test 2) Also 2nd Floor - South Shaft - Fire Damper Inspection Contact Jimmer Brown - ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae1st floor light test on first 2 welds, need to inspect center conection when ready, 2nd floor firedamper and grease duct access doors ok, shaft access door needs to be 20x30
|
Rough-in | 6/20/2016 | 6/21/2016 | 6/21/2016 | P | PART |
Chad Schwendiman
|
|
|
1ST FLOOR - SECURITY ROOM - 2ND LAYER FIRE WRAP INSPECTION CALL JIM BROWN - ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae 2nd layer of fire wrap okay in security room
|
Rough-in | 6/16/2016 | 6/20/2016 | 6/20/2016 | P | PASS |
Ben Livingston
|
|
|
1st floor - women''s bathroom, 2nd layer fire wrap. 1st floor - security room, 1st layer fire wrap. Call Jim Brown at ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae / 2nd layer fire wrap okay
|
Rough-in | 6/17/2016 | 6/20/2016 | 6/20/2016 | A | PASS |
Ben Livingston
|
|
|
Fire access room light test #1. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaaelite test elbow and 2' duct okay, 1st floor from bottum of shaft to out side of mech 1st layer firewrap okay x2
|
Rough-in | 6/16/2016 | 6/17/2016 | 6/17/2016 | A | PART |
Chad Schwendiman
|
|
|
1st Floor - Security Room - Grease Duct Light Test Call Jim Brown at ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae Grease duct light test pass on transitions and 90's out of the north shaft on 1st floor
|
Rough-in | 6/15/2016 | 6/16/2016 | 6/16/2016 | P | PART |
Chad Schwendiman
|
|
|
1st Floor - 1st layer of fire wrap inspection above bathroom. Contact Jim Brown - ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer okay
|
Rough-in | 6/14/2016 | 6/15/2016 | 6/15/2016 | P | PART |
Chad Schwendiman
|
|
|
9th floor bathroom rough in inspection. Please call Jim Brown at ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover bathroom ceilings
|
Rough-in | 6/14/2016 | 6/16/2016 | 6/15/2016 | A | CANC |
Chad Schwendiman
|
|
|
1st Floor - 1st layer of fire wrap inspection above bathroom. Contact Jim Brown - ###-#### Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Inspection cancelled from web by: Melissa Kaae
|
Rough-in | 6/14/2016 | 6/15/2016 | 6/15/2016 | A | PART |
Chad Schwendiman
|
|
|
Clearwater grease duct light inspection. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - grease duct light test pass on duct from south shaft to the grease duct in buffalo wild wings.
|
Rough-in | 6/9/2016 | 6/10/2016 | 6/10/2016 | P | CANC |
Chad Schwendiman
|
|
|
Clearwater grease duct light inspection. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Roger called me and canceled this inspection
|
Rough-in | 6/3/2016 | 6/3/2016 | 6/3/2016 | P | PART |
Chad Schwendiman
|
|
|
2nd layer fire wrap on grease duck. On site contact: Jim Brown Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer fire wrap on grease duct in shaft of gbad pass
|
Rough-in | 5/31/2016 | 6/1/2016 | 6/1/2016 | A | PART |
Chad Schwendiman
|
|
|
Grease duct fire wrap. Onsite contact: Jim Brown. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer pass on 28x18 grease duct in gbad
|
Rough-in | 5/23/2016 | 5/24/2016 | 5/24/2016 | A | PART |
Chad Schwendiman
|
|
|
Early AM inspection for GBAD Shaft Grease Duct. Contact Jim Brown - ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae - Light test pass on last joint of 28x18 in the shaft of gbad. 4th and 5th floor core and shell bathroom ceilings okay to cover. framing on core and shell fire/smoke dampers okay 2nd floor through 6th floor
|
Rough-in | 5/20/2016 | 5/23/2016 | 5/23/2016 | P | PART |
Chad Schwendiman
|
|
|
Call Jim Brown - PM Inspection. Cell Phone - ###-#### Core ; Shell - Clearwater Building - Shell Restroom Ceilings Level 2 Level 3 Level 4 Level 5 Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover core and shell bathroom ceilings on 6th floor, 3rd floor, 2nd floor. okay to cover shaft wall on north shaft o 2nd floor.
|
Rough-in | 5/20/2016 | 5/23/2016 | 5/23/2016 | A | PART |
Chad Schwendiman
|
|
|
Early AM inspection for 2nd Layer Fire Wrap - GBAD Shaft Grease Duct. 56"x18". Contact Jim Brown - ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer fire wrap on the joints of the 50" grease duct pass
|
Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | P | CANC |
Chad Schwendiman
|
|
|
first layer fire wrap insulation duct // Please contact Jim Brown for inspection. Fire Damper inspection for Clearwater Building 2nd Floor and 4th Floor, thanks. Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Rough-in | 5/19/2016 | 5/20/2016 | 5/20/2016 | A | PART |
Chad Schwendiman
|
|
|
Please contact Jim Brown for inspection. Cover inspection for Clearwater Building 5th Floor Restrooms, thanks. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Light test pass on 28x18 grease duct, 1st layer fire wrap pass on 50x18 joints, 9th floor core and shell fire/smoke dampers pass, 8th floor core fire/smoke dampers and bathroom ceilings pass, 7th floor core fire/smoke dampers pass, 6th floor north shaft walls okay to cover, 4th floor shaft walls okay to cover on both shafts, 2nd floor south shaft walls okay to cover.
|
Rough-in | 5/19/2016 | 5/19/2016 | 5/19/2016 | P | CANC |
Ben Livingston
|
|
|
Please contact Jim Brown for inspection. Cover inspection for Clearwater Building 8th Floor Restrooms. Phone #: ###-#### Inspection requested via web by Melissa Kaae- canc by RM
|
Rough-in | 5/18/2016 | 5/19/2016 | 5/19/2016 | A | PART |
Chad Schwendiman
|
|
|
Jim or Roger ###-#### Phone #: ###-#### - Grease duct light test pass where 24x20 connects to 28x18
|
Rough-in | 5/16/2016 | 5/16/2016 | 5/16/2016 | A | PART |
Chad Schwendiman
|
|
|
Light test 6am - light test pass on last 10' section of 50x18, 90 at the bottom, and 90 on 10' of 28x18
|
Rough-in | 5/13/2016 | 5/13/2016 | 5/13/2016 | P | PART |
Chad Schwendiman
|
|
|
Re-inspection of the following. Did not have access doors in for FSD''s. Clear Water Core ; shell above ceiling, rough- in inspection for hard lid in the restrooms for the 6th floor ; 7th floor contact person is Jim Brown @ ###-#### Phone #: ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to cover bathroom hard lid ceilings on the 6th and 7th floors
|
Rough-in | 5/12/2016 | 5/13/2016 | 5/13/2016 | A | FAIL |
Chad Schwendiman
|
|
|
Clear Water Core ; shell above ceiling, rough- in inspection for hard lid in the restrooms for the 6th floor ; 7th floor for tomorrow late morning contact person is Jim Brown @ ###-####
Phone #: ###-#### Inspection requested via web by Melissa Kaae - Need to install duct mounted access doors for fire/smoke dampers
|
Rough-in | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | PASS |
Chad Schwendiman
|
|
|
Roger-grease duct accesss door inspection-inspection time is 6:00 AM Phone #: ###-#### - all access doors on the north and south shafts of clearwater
|
Rough-in | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | PART |
Chad Schwendiman
|
|
|
Roger-2nd layer fire wrap-inspection time is 6:00 AM Phone #: ###-#### - 2nd layer fire wrap pass on 28x18 grease duct 3ea. 10' long, 1ea. 20'long
|
Rough-in | 5/11/2016 | 5/12/2016 | 5/12/2016 | A | PART |
Chad Schwendiman
|
|
|
Roger-grease duct light inspection-inspection time is 6:00 AM Phone #: ###-#### - Light test pass on the 2 10' joints and the transition for the 20x24
|
Rough-in | 5/10/2016 | 5/10/2016 | 5/10/2016 | P | PART |
Chad Schwendiman
|
|
|
1st Layer Grease Duct Wrap. Contact Roger Elam for questions. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer grease duct wrap okay on 20' long 28x18 and 2 each 10' long 28x18
|
Rough-in | 5/5/2016 | 5/6/2016 | 5/6/2016 | A | PART |
Chad Schwendiman
|
|
|
2nd layer fire wrap on grease duct. Please contact Roger Elam for questions. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer fire wrap approved on 20' of 50x18, and 3 each 10' long 50x18
|
Rough-in | 5/4/2016 | 5/5/2016 | 5/5/2016 | P | FAIL |
Chad Schwendiman
|
|
|
2nd layer fire wrap on grease duct. Please contact Roger Elam for questions. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Need to repair fire wrap where it was damaged from the weld pins
|
Rough-in | 5/5/2016 | 5/5/2016 | 5/5/2016 | P | FAIL |
Chad Schwendiman
|
|
|
Fire/smoke damper framing inspection on shafts in the clear water bldg - Framing around fire dampers fail on the north shaft on 6th and 7th floor.
|
Rough-in | 5/5/2016 | 5/5/2016 | 5/5/2016 | P | PASS |
Chad Schwendiman
|
|
|
Fire/smoke damper framing inspection on shafts in the clear water bldg - okay to cover both north and south shaft walls on 9, 8, 5, 3, Okay to cover just south shaft walls on 7th, and 6th
|
Rough-in | 5/3/2016 | 5/4/2016 | 5/4/2016 | A | PART |
Ben Livingston
|
|
|
1st layer fire wrap. On site contact: Roger Elam. Phone #: ###-#### Inspection requested via web by Melissa Kaae- 50x18 greese duct 1 20' 3 10' no 90s were wrapt. 1 layer only
|
Rough-in | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | PART |
Chad Schwendiman
|
|
|
District Building Grease Duct Light Test Inspection - Please contact Roger Elam - ###-#### - Light test pass on 1 each 20' long 28x18, 1 each 10' long 22x24, 2 each 22x24 90's, 3 each 10' long 28x18
|
Rough-in | 5/2/2016 | 5/3/2016 | 5/3/2016 | A | NR |
Chad Schwendiman
|
|
|
1st layer fire wrap. On site contact: Roger Elam Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Rough-in | 5/2/2016 | 5/2/2016 | 5/2/2016 | P | PART |
Chad Schwendiman
|
|
|
District Building Grease Duct Light Test Inspection - Please contact Roger Elam - ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae - light test pass on 50x18 grease duct 4 each 10' long, 1 each 20' long with a 90, and 1 each 90.
|
Rough-in | 4/28/2016 | 5/3/2016 | 5/2/2016 | A | CANC |
Chad Schwendiman
|
|
|
Please contact Roger Elam This is a second layer fire wrap inspection on grease duct. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Inspection cancelled from web by: Melissa Kaae
|
Rough-in | 4/29/2016 | 5/2/2016 | 5/2/2016 | A | FAIL |
Chad Schwendiman
|
|
|
District Building Grease Duct Light Test Inspection - Please contact Roger Elam - ###-#### Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Rough-in | 4/28/2016 | 4/29/2016 | 4/29/2016 | P | CANC |
Chad Schwendiman
|
|
|
Please contact Roger Elam This is a first layer fire wrap inspection on grease duct. We requested a AM inspection but the system wouldn''t allow us to set it up. Really need AM inspection. Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Conference | 4/29/2016 | 4/29/2016 | 4/29/2016 | P | DONE |
Chad Schwendiman
|
|
|
Met on site to discuss light testing the grease duct for the shaft in gbad area. we are ging to light test as much as we can on the ground. They are going to hoist the duct up from the ground floor and we will test the joints as they connect them at the 1st floor location. I also discussed with them that from now on anytime a correction from a previous inspection is not made when we come out to inspect the same item there will be a reinspection fee issued.
|
Rough-in | 4/28/2016 | 4/29/2016 | 4/29/2016 | A | FAIL |
Chad Schwendiman
|
|
|
Please contact Roger Elam - Cell - ###-#### This is a grease duct light test per agreement. 3rd party light test results will be emailed to Chad S. Phone #: ###-#### Inspection requested via web by Melissa Kaae Need to complete a light test with Boise city. This work wasn't approved for 3rd party testing
|
Conference | 4/21/2016 | 4/21/2016 | 4/21/2016 | A | DONE |
Chad Schwendiman
|
|
|
Please contact Roger Elam or Pat Nichols (###-####). Would like to discuss grease duct inspections that would happen progressively as installation happens Phone #: ###-#### Inspection requested via web by Melissa Kaae
|
Rough-in | 4/7/2016 | 4/8/2016 | 4/8/2016 | P | NR |
Ben Livingston
|
|
|
4th floor through 6th floor fire dampers. On site contact: Rob Butler. Phone #: ###-#### Inspection requested via web by Melissa Kaae- framing around firesmoke dampers needs to be corrected, this is the second time we have done a inspection where no corrections were made.
|
Rough-in | 3/31/2016 | 4/1/2016 | 4/1/2016 | P | PART |
Chad Schwendiman
|
|
|
Fire wrap. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer fire wrap pass on grease duct in south shaft on the 1st floor
|
Rough-in | 3/29/2016 | 3/31/2016 | 3/31/2016 | P | PART |
Chad Schwendiman
|
|
|
Fire wrap. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer fire wrap okay on 1st floor south shaft.
|
Rough-in | 3/29/2016 | 3/30/2016 | 3/30/2016 | P | PART |
Chad Schwendiman
|
|
|
Fire wrap. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer fire wrap pass on the 1st floor south shaft
|
Rough-in | 3/29/2016 | 3/30/2016 | 3/29/2016 | P | CANC |
Chad Schwendiman
|
|
|
On site contact: Pat Nichols. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Inspection cancelled from web by: Melissa Kaae
|
Rough-in | 3/24/2016 | 3/25/2016 | 3/25/2016 | A | PART |
Chad Schwendiman
|
|
|
Shaft wall fire damper framing. On site contact: Rob Butler Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to insulate supply loops on 5th, 6th, and 7th floors. 1st floor exhaust shaft on east exterior wall okay to cover. Clearance to framing on fire dampers fail
|
Rough-in | 3/17/2016 | 3/17/2016 | 3/17/2016 | A | PART |
Chad Schwendiman
|
|
|
2nd floor exhaust shaft - okay to cover exhaust shafts on the east exterior wall on the 2nd floor
|
Rough-in | 3/15/2016 | 3/16/2016 | 3/16/2016 | A | PART |
Chad Schwendiman
|
|
|
On site contact: Rob Butler. Phone #: ###-#### Inspection requested via web by Melissa Kaae - okay to insulate duct in 5th floor restrooms
|
Rough-in | 3/2/2016 | 3/3/2016 | 3/3/2016 | A | PART |
Chad Schwendiman
|
|
|
Jim ###-#### - Showers on the east side of the 5th floor ceilings okay to cover
|
Rough-in | 2/29/2016 | 3/1/2016 | 3/1/2016 | A | PART |
Chad Schwendiman
|
|
|
Grease duct insulation. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer fire wrap okay on 9th floor both shafts
|
Rough-in | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | PEND |
Chad Schwendiman
|
|
|
Partial shaft duct inspection. On site contact: Rob Butler Phone #: ###-#### Inspection requested via web by Melissa Kaae - need to install fire/smoke dampers and call for a rough in inspection to check clearances to framing.
|
Rough-in | 2/29/2016 | 2/29/2016 | 2/29/2016 | P | CANC |
Chad Schwendiman
|
|
|
Grease duct insulation. On site contact: Pat Nichols. Phone #: ###-#### >> Inspection requested via web by Melissa Kaae Inspection cancelled from web by: Melissa Kaae
|
Rough-in | 2/24/2016 | 2/26/2016 | 2/26/2016 | A | PART |
Chad Schwendiman
|
|
|
Greaser duct fire wrap inspection - 2nd layer pass on both shafts on the 6th and 7th floors. 1st layer pass on the 8th floor both shafts.
|
Rough-in | 2/22/2016 | 2/23/2016 | 2/23/2016 | A | PART |
Chad Schwendiman
|
|
|
Grease duct fire wrap inspection. Dennis ###-#### - 5th floor north shaft 2nd layer okay, 7th floor 1st layer on both shafts okay
|
Rough-in | 2/19/2016 | 2/22/2016 | 2/22/2016 | A | PART |
Chad Schwendiman
|
|
|
Grease duct insulation inspection. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer on 5th floor south shaft pass, 1st layer on 6th floor both shafts pass
|
Rough-in | 2/17/2016 | 2/18/2016 | 2/18/2016 | A | PART |
Chad Schwendiman
|
|
|
Grease duct insulation inspection. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer wrap okay on 3rd floor south shaft, & 4th floor south shaft. 1st layer pass on 5th floor both shafts
|
Rough-in | 2/11/2016 | 2/16/2016 | 2/16/2016 | A | PART |
Chad Schwendiman
|
|
|
Grease duct insulation inspection. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 4th floor 1st layer of fire wrap okay
|
Rough-in | 2/9/2016 | 2/11/2016 | 2/11/2016 | A | PART |
Chad Schwendiman
|
|
|
Grease duct insulation inspection. On site contact: Pat Nichols. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 2nd layer grease duct wrap on 2nd floor both shafts, 2nd layer wrap on 3rd floor north shaft, 1st layer wrap on 3rd floor south shaft pass.
|
Rough-in | 2/4/2016 | 2/5/2016 | 2/5/2016 | A | PASS |
Chad Schwendiman
|
|
|
Fire wrap inspection north and south shaft 2nd floor. Contact Pat Nichols for questions. Phone #: ###-#### Inspection requested via web by Melissa Kaae - 1st layer of grease duct wrap on the 2nd floor pass
|
Rough-in | 2/3/2016 | 2/3/2016 | 2/3/2016 | P | PASS |
Chad Schwendiman
|
|
|
Light test. On site contact: Pat Nichols. 3rd Party grease duct light-test was sent to Bill Vandergrift and Chad Schwindemian on 2/2/16. Please email me to get copy of duct test report. Phone #: ###-#### Inspection requested via web by Melissa Kaae - I did receive the report and it is in the documents attached to the mec permit
|
Rough-in | 2/2/2016 | 2/2/2016 | 2/2/2016 | P | PASS |
Chad Schwendiman
|
|
|
Rough-In Cover. On site contact: Pat Nichols Phone #: ###-#### Inspection requested via web by Melissa Kaae - Rust removal complete
|
Rough-in | 2/2/2016 | 2/2/2016 | 2/2/2016 | A | PART |
Chad Schwendiman
|
|
|
Inspect rust removal on grease duct - still need to remove the rust from the grease duct in the south shaft on the 4th floor. everything else is good.
|
Conference | 1/27/2016 | 2/1/2016 | 2/1/2016 | A | PART |
Bill VanDegrift
|
|
|
Meet on site at 11:00 will get third party grease duct light test
|
Conference | 1/27/2016 | 2/1/2016 | 2/1/2016 | A | DONE |
Chad Schwendiman
|
|
|
meet on site 11:00 - met with Bill, Troy, and RM on site to address the testing of the grease ducts. It was decided that they will use a approved third party testing agency for the testing of the grease duct and supply a report from the third party to the city for approval.
|
Conference | 1/27/2016 | 2/1/2016 | 2/1/2016 | A | DONE |
Troy James
|
|
|
Meet on site at 11:00
|
Rough-in | 11/18/2015 | 11/18/2015 | 11/18/2015 | P | PART |
Chad Schwendiman
|
|
|
For cover. On site contact: Rob Butler Phone #: ###-#### Inspection requested via web by Melissa Kaae - high pressure supply loop on 4th, 5th floors okay to insulate
|
Rough-in | 11/9/2015 | 11/10/2015 | 11/10/2015 | A | PART |
Chad Schwendiman
|
|
|
For cover. On site contact: Rob Butler. Phone #: ###-#### Inspection requested via web by Melissa Kaae - Okay to insulate the high pressure supply loop on the 2nd, and 3rd floor
|
Rough-in | 10/21/2015 | 10/26/2015 | 10/26/2015 | A | FAIL |
Troy James
|
|
|
Grease duct light test for (4) ducts. On site contact: Rob Butler Phone #: ###-#### Inspection requested via web by Melissa Kaae physically unable to complete light test on grease duct due to the construction. Contractor to provide air test to grease duct.
|