Pressure Test | 11/11/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Chad Schwendiman
|
|
|
Pressure test for PVC flue for upstairs unit. Phone #: ###-#### Inspection requested via web by Bryan Palmer
|
Final | 11/11/2015 | 11/12/2015 | 11/12/2015 | P | PASS |
Chad Schwendiman
|
|
|
Mechanical final after flue pressure test. Please call Monte at ###-#### 1/2 hr. ahead of inspection so we can have someone present to reassemble the flue. Phone #: ###-#### Inspection requested via web by Bryan Palmer
|
Rough-in | 7/21/2015 | 7/21/2015 | 7/21/2015 | P | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer
|
Rough-in | 7/20/2015 | 7/21/2015 | 7/21/2015 | A | FAIL |
Eric Strole
|
|
|
Pressure test on upstairs flue. Phone #: ###-#### Inspection requested via web by Bryan Palmer-Fresh air needs come off the return air plenum and cannot go out thru the roof.
|
Pressure Test | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | PART |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer - 60lb gas pass, 20lb gas pass, 5lb flue pass for the furnace in the garage, still need to pressure test pvc flue for furnace in the upstairs
|
Rough-in | 7/16/2015 | 7/17/2015 | 7/17/2015 | A | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer - crawl is not complete, need to pressure test the pvc flue for the upstairs unit.
|