Final | 9/3/2015 | 9/3/2015 | 9/3/2015 | P | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Troy Worley
|
Rough-in | 7/15/2015 | 7/16/2015 | 7/16/2015 | A | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Troy Worley
|
Pressure Test | 7/14/2015 | 7/14/2015 | 7/14/2015 | A | PASS |
Eric Strole
|
|
|
Phone #: ###-#### Inspection requested via web by Troy Worley-20 lb gas test pass
|
Rough-in | 7/14/2015 | 7/14/2015 | 7/14/2015 | A | FAIL |
Eric Strole
|
|
|