Final | 11/30/2015 | 12/2/2015 | 12/2/2015 | P | PASS |
Chad Schwendiman
|
|
|
Final on permanent boiler. Eric Sonner site Foreman Phone #: ###-#### Inspection requested via web by Joshua Bennett
|
Final | 10/7/2015 | 10/8/2015 | 10/8/2015 | P | PART |
Chad Schwendiman
|
|
|
Site contact will be Eric Sonner. Please call when on the way and he will meet you there. Phone #: ###-#### Inspection requested via web by Joshua Bennett - Temporary occupancy okay. Waiting on Boiler to get here and be installed, using a temporary boiler until then.
|
Pressure Test | 9/17/2015 | 9/18/2015 | 9/18/2015 | A | PASS |
Chad Schwendiman
|
|
|
Gas pipe inspection. Please contact Phil Britain for directions or meeting ###-####. If possible a inspection in the afternoon of Thursday September 17th would be appreciated. Phone #: ###-#### Inspection requested via web by Joshua Bennett - 60lb gas pass
|
Conference | 9/10/2015 | 9/11/2015 | 9/11/2015 | P | DONE |
Chad Schwendiman
|
|
|
Inspection of ducting pre insulation Phone #: ###-#### Inspection requested via web by Joshua Bennett - okay to insulate duct for north unit on exterior of the building
|
Conference | 9/4/2015 | 9/8/2015 | 9/8/2015 | P | PART |
Chad Schwendiman
|
|
|
Site Foreman is Eric Sonner. Inspection of duct Phone #: ###-#### Inspection requested via web by Joshua Bennett - okay to insulate duct on outside of building on the south unit.
|