Final | 3/10/2016 | 3/10/2016 | 3/10/2016 | P | PASS |
Ben Livingston
|
|
|
Hydronic final. Piping complete and Cryro Tech info on site for boiler fluid Phone #: ###-#### Inspection requested via web by Scott Sparrell
|
Final | 3/7/2016 | 3/8/2016 | 3/8/2016 | A | CANC |
Bill VanDegrift
|
|
|
not ready
|
Final | 3/7/2016 | 3/7/2016 | 3/7/2016 | P | PART |
Bill VanDegrift
|
|
|
needs to lable the hydronic system per appendix L of the plumbing code
|
Pressure Test | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | PASS |
Dixie Fellows
|
|
|
2---100lb hydronic tests ok
|
Rough-in | 8/31/2015 | 8/31/2015 | 8/31/2015 | P | PASS |
Dixie Fellows
|
|
|
Scott-###-####
|
Rough-in | 8/28/2015 | 8/28/2015 | 8/28/2015 | P | FAIL |
Dixie Fellows
|
|
|
Hydronic tubing install for 11 zones with two manifold locations. Tubing pressure test verification for cover. Phone #: ###-#### >> Inspection requested via web by Scott Sparrell..guage must be a 100 psi
|