Final | 6/30/2016 | 7/1/2016 | 7/1/2016 | A | PASS |
Chad Schwendiman
|
|
|
Call Curt at ###-#### 30 minutes in advance for access. 8AM is the best time before Library opens. Phone #: ###-#### Inspection requested via web by Joel Stobie
|
Rough-in | 6/13/2016 | 6/14/2016 | 6/14/2016 | A | PART |
Chad Schwendiman
|
|
|
Call Gary at ###-#### for access. Priority is to review built out "privacy rooms" on 2nd floor for temp occupancy. Can also review ERVs and VRF on 2nd floor and basement mechanical. New install is 98% complete, removal of old units is in progress. Phone #: ###-#### Inspection requested via web by Joel Stobie - The 2nd floor final on privacy rooms okay
|
Rough-in | 4/22/2016 | 4/25/2016 | 4/25/2016 | P | PART |
Ben Livingston
|
|
|
Rough-in inspection for mechanical chase (2nd floor, East wall) to be sheetrocked in this week. Phone #: ###-#### Inspection requested via web by Joel Stobie- 2nd floor north east shaft ok to cover
|
Rough-in | 4/8/2016 | 4/11/2016 | 4/11/2016 | A | PART |
Chad Schwendiman
|
|
|
Please contact Gary Duncan for site access and review. Cell Phone# ###-####. Phone #: ###-#### Inspection requested via web by Joshua Bennett - okay to cover hard lid in hallway to mechanical room on the 2nd floor
|