Final | 2/23/2017 | 2/23/2017 | 2/23/2017 | P | PASS |
Ben Livingston
|
|
|
Please call Tom with any questions Phone #: ###-#### Inspection requested via web by Diane Day
|
Mec-Aging Inspection | 2/15/2017 | 2/15/2017 | 2/15/2017 | | CANC |
Ben Livingston
|
|
|
|
Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 | A | PASS |
Ben Livingston
|
|
|
2ND FLOOR ROUGH IN THANK YOU Phone #: ###-#### Inspection requested via web by Dustin Rich
|
Rough-in | 10/28/2016 | 10/28/2016 | 10/28/2016 | P | CANC |
Ben Livingston
|
|
|
2nd floor rough in inspection please thank you Phone #: ###-#### Inspection requested via web by Dustin Rich need 2nd floor changes resubmitted to city for approval
|
Rough-in | 8/31/2016 | 9/1/2016 | 9/1/2016 | P | PASS |
Ben Livingston
|
|
|
3rd floor rough-in Phone #: ###-#### Inspection requested via web by Dustin Rich- 3rd floor ok to cover
|
Rough-in | 8/30/2016 | 8/31/2016 | 8/31/2016 | A | PART |
Ben Livingston
|
|
|
THIRD FLOOR INSPECTION PLEASE THANK YOU Phone #: ###-#### Inspection requested via web by Dustin Rich- 3rd floor ok, need to see the back side of firedampers before they are covered
|
Rough-in | 8/29/2016 | 8/30/2016 | 8/30/2016 | A | CANC |
Ben Livingston
|
|
|
THIRD FLOOR ROUGH IN INSPECTION >> Inspection requested via web by Dustin Rich Inspection cancelled from web by: Dustin Rich
|
Rough-in | 8/25/2016 | 8/25/2016 | 8/25/2016 | P | CANC |
Ben Livingston
|
|
|
|
Rough-in | 8/24/2016 | 8/25/2016 | 8/25/2016 | P | PART |
Ben Livingston
|
|
|
This is for a 3rd floor rough in inspection. Tom will be showing up there about 12:45. His # is ###-####. Thanks! Inspection requested via web by Dustin Rich need all dryer vents need 2x4 walls, firedampers need 18gage angle around them, clearances ok, exterior walls ok to insulate.
|
Conference | 8/19/2016 | 8/19/2016 | 8/19/2016 | P | DONE |
Chad Schwendiman
|
|
|
Met Ben on site to go over the approved plans
|
Conference | 8/19/2016 | 8/19/2016 | 8/19/2016 | P | CANC |
Ben Livingston
|
|
|
|
Rough-in | 8/16/2016 | 8/18/2016 | 8/18/2016 | A | NR |
Eric Strole
|
|
|
Please inspect 3rd floor for cover. Inspection requested via web by Dustin Rich-Corrections not complete. Need approved plans on site for next inspection.
|
Conference | 8/18/2016 | 8/18/2016 | 8/18/2016 | A | CANC |
Ben Livingston
|
|
|
|
Rough-in | 8/16/2016 | 8/17/2016 | 8/16/2016 | A | CANC |
Eric Strole
|
|
|
inspect 3rd floor for cover. >> Inspection requested via web by Dustin Rich Inspection cancelled from web by: Dustin Rich
|
Conference | 8/8/2016 | 8/9/2016 | 8/9/2016 | A | CANC |
Ben Livingston
|
|
|
|
Conference | 8/8/2016 | 8/9/2016 | 8/9/2016 | A | CANC |
Eric Strole
|
|
|
|
Rough-in | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PART |
Eric Strole
|
|
|
THANK YOU Phone #: ###-#### Inspection requested via web by Dustin Rich-Missing sheetrock on side of fire damper. Need to have tibble engineer kitchen and bath exhaust 2nd flr in fire rated assembly that is not on approved plans. All dryer exhausts need to be in a minimum of a 4" wall.
|
Pressure Test | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | CANC |
Eric Strole
|
|
|
THANK YOU Phone #: ###-#### Inspection requested via web by Dustin Rich-Flue test not required
|
Conference | 8/2/2016 | 8/2/2016 | 8/2/2016 | A | PART |
Ben Livingston
|
|
|
did conference with Eric need 2nd floor changes resubmitted
|
Pressure Test | 7/28/2016 | 8/2/2016 | 8/1/2016 | P | CANC |
Eric Strole
|
|
|
FLU PRESSURE TEST Phone #: ###-#### >> Inspection requested via web by Dustin Rich Inspection cancelled from web by: Dustin Rich
|
Rough-in | 7/28/2016 | 8/2/2016 | 8/1/2016 | P | CANC |
Eric Strole
|
|
|
3RD FLOOR ONLY ROUGH IN PLEASE. Phone #: ###-#### >> Inspection requested via web by Dustin Rich Inspection cancelled from web by: Dustin Rich
|
Rough-in | 7/1/2016 | 7/6/2016 | 7/6/2016 | P | PASS |
Ben Livingston
|
|
|
DUCTING INSPECTION INSTALLER: TOM ###-#### THANK YOU Phone #: ###-#### Inspection requested via web by Dustin Rich- fire dampers have been corrected
|
Rough-in | 6/29/2016 | 6/29/2016 | 6/29/2016 | P | PART |
Chad Schwendiman
|
|
|
This is for a seal inspection Inspection requested via web by Dustin Rich- 3rd floor duct ok to ins. fire dampers need to be installed permanufacture instruction
|
Conference | 6/20/2016 | 6/20/2016 | 6/20/2016 | A | DONE |
Eric Strole
|
|
|
Please see Tom on site. He has some questions. His phone number is ###-#### Inspection requested via web by Dustin Rich-Conferance to see if duct seal inspection is required. Yes.
|