Mec-Aging Inspection | 1/15/2018 | 1/15/2018 | 1/16/2018 | | PASS |
Chad Schwendiman
|
|
|
|
DOC - Permit Finaled | 1/16/2018 | 1/16/2018 | 1/16/2018 | A | PASS |
Chad Schwendiman
|
|
|
|
Final | 10/16/2017 | 10/18/2017 | 10/18/2017 | A | PART |
Chad Schwendiman
|
|
|
02 rooms final Phone #: ###-#### Inspection requested via web by Brandon Sorensen - 02 rooms okay. temporary occupancy of the whole building okay. Need to complete condensate fix on pool dehumidification unit
|
Final | 10/16/2017 | 10/17/2017 | 10/16/2017 | A | CANC |
Ben Livingston
|
|
|
02 rooms final Phone #: ###-#### Inspection requested via web by Brandon Sorensen
|
Final | 10/6/2017 | 10/6/2017 | 10/6/2017 | A | PART |
Chad Schwendiman
|
|
|
Carey ###-#### - Everything is complete except for F-4 condensate, and the 02 rooms
|
Final | 9/26/2017 | 9/27/2017 | 9/27/2017 | A | FAIL |
Chad Schwendiman
|
|
|
TCO - Call Cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - 1. Still need Generator commisioning report. 2. Need air balance report for 1st floor and stairway pressurization
|
Final | 9/18/2017 | 9/19/2017 | 9/19/2017 | A | FAIL |
Chad Schwendiman
|
|
|
Call Cary for access Phone #: ###-#### Inspection requested via web by David Tully - 1. Condensate needs to be completed on AC-1 2. Need a copy of the generator commisioning report. 3. Make up air damper for pool equipment and storage room is not hooked up. 4. Need to complete the armaflex and UV protection on the 3rd floor roof. 5. AC's on third floor roof not hooked up or running. 6. third floor air balance not complete. 7. Need to complete condensate piping for pool heaters. 8. Gas flex not allowed to penetrate the outside of the dehumidification unit. 9. plumbing vent on roof needs to be 10' away or 3' above fresh air intake. 10. Need preliminary air balance report to verify ventilation in occupied area's
|
Rough-in | 8/9/2017 | 8/10/2017 | 8/10/2017 | A | PASS |
Chad Schwendiman
|
|
|
RI inspection for the O2 rooms. Call Cary for access. Phone #: ###-#### Inspection requested via web by David Tully - 402, 502, 602, 702, 802, 902, 1002 okay to cover
|
Rough-in | 8/3/2017 | 8/4/2017 | 8/4/2017 | A | PASS |
Chad Schwendiman
|
|
|
Cover Inspection first floor. Call Cary for access. Phone #: ###-#### Inspection requested via web by David Tully - Managers office grid okay to cover, cove heaters on 2nd floor okay to cover, pool filter room okay, elevator lobby on 2nd floor okay to cover, prefuction grid okay to cover, fitness room grid okay to cover.
|
Rough-in | 7/14/2017 | 7/17/2017 | 7/17/2017 | A | PASS |
Chad Schwendiman
|
|
|
misc - 1st floor Phone #: ###-#### Inspection requested via web by Brandon Sorensen - Kitchen, 1st floor laundry room, drive through, 3rd floor hallway, and 10th floor hallway ceilings are okay to cover. Ductwork on generator okay.
|
Rough-in | 6/19/2017 | 6/20/2017 | 6/20/2017 | A | PASS |
Chad Schwendiman
|
|
|
Misc stuff - as per Cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - 3rd floor pool room and conference room ceilings okay to cover. elevator lobby's okay to cover on 3rd floor, and 5th through 10th floors. 10th floor conference room and bathroom ceilings okay to cover
|
Rough-in | 5/26/2017 | 5/30/2017 | 5/30/2017 | A | PASS |
Chad Schwendiman
|
|
|
Misc items on 1st and 10th floors Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover the remaining hard lids on the 1st floor. okay to cover room 325, and 3rd floor hard lids. Okay to cover cooridoor grid ceilings on 4th through 8th floors.
|
Rough-in | 5/12/2017 | 5/15/2017 | 5/15/2017 | A | PASS |
Chad Schwendiman
|
|
|
10th floor rooms - West Side Phone #: ###-#### Inspection requested via web by Brandon Sorensen - Okay to cover guest rooms on the west side of the 10th floor.
|
Rough-in | 5/9/2017 | 5/10/2017 | 5/10/2017 | A | PASS |
Chad Schwendiman
|
|
|
2nd layer shaft 10th floor Phone #: ###-#### Inspection requested via web by Brandon Sorensen - mechanical shafts okay for 2nd layer on 10th floor, subduct shaft okay on 3rd floor, okay to cover ceiling where mechanical shaft is behind elevators on the 1st floor
|
Rough-in | 5/4/2017 | 5/5/2017 | 5/5/2017 | A | PASS |
Chad Schwendiman
|
|
|
shaft inspection 1st floor Phone #: ###-#### Inspection requested via web by Brandon Sorensen - framing around dampers behind elevator on 1st floor okay
|
Rough-in | 5/4/2017 | 5/4/2017 | 5/4/2017 | A | PART |
Chad Schwendiman
|
|
|
Okay to cover 1st floor loby ceilings except for mechanical shaft behind the elevators
|
Rough-in | 5/2/2017 | 5/3/2017 | 5/3/2017 | A | PASS |
Chad Schwendiman
|
|
|
10th floor sub duct shaft - call cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover 10th floor sub duct shafts and guest rooms on the east side of the corridoor
|
Rough-in | 5/1/2017 | 5/2/2017 | 5/2/2017 | A | PART |
Chad Schwendiman
|
|
|
Misc stuff - call Cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - flue for pool heaters okay, generator dampers okay, Need to remove sheetrock from sub duct shafts on the 10th floor, need to remove pvc from subduct shaft on the 3rd floor, need access doors completed in hard lids on 1st floor.
|
Rough-in | 4/24/2017 | 4/25/2017 | 4/25/2017 | A | PASS |
Chad Schwendiman
|
|
|
West Side 9th floor rough in - call Cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover guest rooms on the 9th floor except for 902, okay for 2nd layer on shaft wall on 3rd floor behind the elevator
|
Rough-in | 4/18/2017 | 4/19/2017 | 4/19/2017 | A | PART |
Chad Schwendiman
|
|
|
sub duct shaft in fire riser room - call cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay for 1st layer of shaft wall on mechanical shafts on the 10th floor, okay to cover subduct shafts in fire riser rooms except for 3rd floor where shaft isn't complete
|
Rough-in | 4/13/2017 | 4/14/2017 | 4/14/2017 | A | PART |
Chad Schwendiman
|
|
|
Misc 9th floor Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover subduct shafts on 9th floor, okay for 2nd layer of sheetrock on mechanical shafts on the 9th floor. okay to cover guest rooms on east side of corridoor on 9th floor
|
Rough-in | 4/5/2017 | 4/6/2017 | 4/6/2017 | A | PART |
Chad Schwendiman
|
|
|
Call Cary for access.8th floor rough in. Phone #: ###-#### Inspection requested via web by David Tully - okay for 1st layer of shaft wall on mechanical shafts on the 9th floor. okay for 2nd layer on mechanical shafts on 8th floor. okay to cover guest rooms on 8th floor except for 802
|
Rough-in | 3/27/2017 | 3/28/2017 | 3/28/2017 | A | PART |
Chad Schwendiman
|
|
|
7th floor rooms Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to insulate duct in hallway on 8th, and 9th floors. Okay to for 1st layer and framing around dampers on 8th floor. okay to cover guest rooms 701, 723, 727
|
Rough-in | 3/22/2017 | 3/23/2017 | 3/23/2017 | A | PART |
Chad Schwendiman
|
|
|
7th floor rooms Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover guest rooms on the 7th floor except for 701, 723, and 727. okay to cover subduct shafts on 8th floor. okay to cover framing around fire dampers on 7th floor, and 1st floor except for the mechanical shaft behind elevator on 1st floor.
|
Rough-in | 3/20/2017 | 3/21/2017 | 3/21/2017 | A | PART |
Chad Schwendiman
|
|
|
3rd floor water heater flue piping Phone #: ###-#### Inspection requested via web by Brandon Sorensen - pool heater flues okay to cover, room 627 okay to cover, okay to cover mechanical shaft behind elevators on 9th, and 10th floors
|
Rough-in | 3/15/2017 | 3/16/2017 | 3/16/2017 | A | PART |
Chad Schwendiman
|
|
|
6th and 7th floor shafts. Call Cary for access. Phone #: ###-#### Inspection requested via web by David Tully - okay to put up shaft wall on mechanical shafts on 6th, and 7th floor. framing around fire dampers on 5th floor okay to cover
|
Rough-in | 3/14/2017 | 3/15/2017 | 3/15/2017 | A | PART |
Chad Schwendiman
|
|
|
6th floor west side rooms, 5th floor chases - call cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - guest rooms on 6th floor okay except for 602, and 627, fire/smoke damper framing okay on 5th floor
|
Rough-in | 3/9/2017 | 3/10/2017 | 3/10/2017 | A | PART |
Chad Schwendiman
|
|
|
Call Cary for access. Cover for conference room 3rd floor and cover for 6th floor rooms east side. Phone #: ###-#### Inspection requested via web by David Tully - okay to cover guest rooms on the east side of the 6th floor. framing around fire/smoke danpers okay for 3rd floor conference room
|
Rough-in | 3/6/2017 | 3/7/2017 | 3/7/2017 | A | PART |
Chad Schwendiman
|
|
|
Cover Inspection 5th Floor Shafts. Call Cary for access. Phone #: ###-#### Inspection requested via web by David Tully - 5th floor ducts in shafts okay.
|
Rough-in | 2/28/2017 | 3/1/2017 | 3/1/2017 | A | PART |
Chad Schwendiman
|
|
|
Re-inspect shafts 3rd and 4th floor. Call Cary for access. Phone #: ###-#### Inspection requested via web by David Tully - okay to cover fire/smoke dampers in the corridoors on 3rd, and 4th floors. okay to cover guest rooms 427, 428, 528
|
Rough-in | 2/27/2017 | 2/28/2017 | 2/28/2017 | A | PART |
Chad Schwendiman
|
|
|
Call Cary for access need cover for shaft 4th floor and cover for 5th floor. Phone #: ###-#### Inspection requested via web by David Tully - Okay to cover guest rooms on the 5th floor except for rooms 502, 528, need to remove fire caulk from around dampers on the 3rd, and 4th floors.
|
Rough-in | 2/22/2017 | 2/23/2017 | 2/23/2017 | A | PART |
Chad Schwendiman
|
|
|
3rd Floor / West corner Phone #: ###-#### Inspection requested via web by Brandon Sorensen - Okay to cover 3rd floor guest rooms except for rooms 325, and 356
|
Rough-in | 2/14/2017 | 2/15/2017 | 2/15/2017 | A | PART |
Chad Schwendiman
|
|
|
4th floor cover - call cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to cover guest rooms on 4th floor except for 402, 427, 428. Okay to cover guest rooms on the east side of corridoor on the 3rd floor. 2nd layer of fire wrap on the generator exhaust okay
|
Rough-in | 2/9/2017 | 2/10/2017 | 2/10/2017 | A | PART |
Chad Schwendiman
|
|
|
Carrie Phone #: ###-#### - 1st layer fire wrap on generator exhaust okay, sub duct shafts on 4th floor okay to cover, vertical duct shafts on 4th floor okay to cover to the point of verifing framing around dampers.
|
Rough-in | 2/1/2017 | 2/2/2017 | 2/2/2017 | A | PART |
Chad Schwendiman
|
|
|
generator flue venting - call cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - okay to insulate generator exhaust
|
Rough-in | 1/25/2017 | 1/26/2017 | 1/26/2017 | A | FAIL |
Chad Schwendiman
|
|
|
Generator flue inspection - 1st floor - call cary Phone #: ###-#### Inspection requested via web by Brandon Sorensen - need manufactures venting instructions or engineering approval of venting as installed
|
Rough-in | 12/14/2016 | 12/15/2016 | 12/15/2016 | A | FAIL |
Chad Schwendiman
|
|
|
damper inspection Phone #: ###-#### Inspection requested via web by Brandon Sorensen - Need documintation from manufacture of fire smoke dampers detailing framing requirements around dampers at floor penetrations.
|
Conference | 12/2/2016 | 12/2/2016 | 12/2/2016 | A | DONE |
Chad Schwendiman
|
|
|
|
Rough-in | 9/23/2016 | 9/23/2016 | 9/23/2016 | P | PART |
Chad Schwendiman
|
|
|
Okay to cover ceilings in the 2 model rooms on the 4th floor
|
Rough-in | 9/21/2016 | 9/22/2016 | 9/22/2016 | A | FAIL |
Chad Schwendiman
|
|
|
4th model rooms overhead cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen - Need to submitt plan modifications to plan review
|
Conference | 9/22/2016 | 9/22/2016 | 9/22/2016 | A | PEND |
Ben Livingston
|
|
|
Meet to look at 4th model rooms
|