Permit Information
Permit NumberMEC16-03754
StatusFinaled
Name 4 SEASONS HEATING & COOLING INC
Site Address 3304 E ECHO CT
Project Name 
Customer Number 
ePlanReviewNo
Description
Complete HVAC Installation: New construction single level home.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final12/4/201612/5/201612/5/2016APASS
DetailsEric Strole
Please call James at ###-#### with any questions or for access information if the house is locked up, thanks. Inspection requested via web by 4 Seasons
Rough-in9/7/20169/8/20169/8/2016APASS
DetailsChad Schwendiman
Please do the crawl inspection for finishing the rough-in. If you have any questions, call James at ###-####, thanks. Inspection requested via web by 4 Seasons
Rough-in8/31/20169/1/20169/1/2016APART
DetailsBen Livingston
Please do the rough-in inspection. I believe the pressure witness is done because you let the air out. The hood make-up air is the 8" duct from the roof to the plehnum. A motorized damper will be wired in with the hood, The house fresh air is the 8" duct from the soffit to the plehnum. Call James at ###-#### with any questions, thanks. Inspection requested via web by 4 Seasons
20lb gas, 5lb flue, top roughin ok, soffit damper to be installed at trim radiant damper is built into grille.
crawl still needs to be completed
Rough-in8/30/20168/31/20168/31/2016AFAIL
DetailsEric Strole
Please do rough-in and pressure witness. Call James at ###-#### with any questions, thanks. Inspection requested via web by 4 Seasons-Need to complete crawl and hook up all bath exhaust. Need make-up air for 600 cfm kitchen exhaust.