Final | 10/6/2016 | 10/7/2016 | 10/7/2016 | A | PASS |
Chad Schwendiman
|
|
|
As soon as possible will be good. Phone #: ###-#### Inspection requested via web by Drew Tverdy
|
Final | 10/4/2016 | 10/5/2016 | 10/5/2016 | A | PART |
Chad Schwendiman
|
|
|
Hood is good to go. Waiting for the balance report paperwork and I will email it out as soon as I receive it. The only thing not in is the mechanical access panel because I am still waiting for it to show up. 8;00 a.m. will be a good time. I will not be there but the contractor will be but please call with any questions. Phone #: ###-#### Inspection requested via web by Drew Tverdy - tempoarary occupancy okay. Still waiting on access door and air balance report
|
Final | 10/3/2016 | 10/3/2016 | 10/3/2016 | P | FAIL |
Chad Schwendiman
|
|
|
12:30 partial final, mechanical access is not in, Air balance is in the process. My guy will be there to show exhaust blowers. Phone #: ###-#### Inspection requested via web by Drew Tverdy - The exhaust fans and make up air unit need to be running and operational from the hood controls. need air balance report for the hood
|
Rough-in | 9/30/2016 | 9/30/2016 | 9/30/2016 | A | PASS |
Chad Schwendiman
|
|
|
Light test 2 connections and discuss final. Will be ready by 10 a.m. Phone #: ###-#### Inspection requested via web by Drew Tverdy - grease duct okay
|
Rough-in | 9/14/2016 | 9/14/2016 | 9/14/2016 | P | PASS |
Chad Schwendiman
|
|
|
12:30 light test please Phone #: ###-#### Inspection requested via web by Drew Tverdy - grease duct light test pass on duct connection from where it stubs out of shaft down to the hood connection
|
Rough-in | 9/13/2016 | 9/14/2016 | 9/14/2016 | A | PART |
Chad Schwendiman
|
|
|
light test for grease duct. 8:30 please. Phone #: ###-#### Inspection requested via web by Drew Tverdy - light test pass for offset pieces above hood
|
Rough-in | 9/8/2016 | 9/8/2016 | 9/8/2016 | P | PART |
Chad Schwendiman
|
|
|
need to check fire wrap in chase so we can cover. 2:00 should be fine Phone #: ###-#### Inspection requested via web by Drew Tverdy - grease duct fire wrap okay in the shaft. okay to cover shaft
|
Rough-in | 9/1/2016 | 9/1/2016 | 9/1/2016 | P | PART |
Brian Scoles
|
|
|
Fire wrap inspection before chase gets closed up. 1:00 it will be ready Inspection requested via web by Drew Tverdy -2nd floor to roof in chase hallway side- 2 layers ok- need to finish banding on 12 inch spacing- need to reinspect after all is done before final enclosure
|
Rough-in | 8/31/2016 | 9/1/2016 | 9/1/2016 | A | PASS |
Ben Livingston
|
|
|
light test for duct in the chase. as early as possible please. Phone #: ###-#### Inspection requested via web by Drew Tverdy- chase duct ok to start 1st layer fire wrap
|
Rough-in | 8/31/2016 | 8/31/2016 | 8/31/2016 | P | FAIL |
Chad Schwendiman
|
|
|
light test on welds in chase so we can cover. 1:00 would be great. Inspection requested via web by Drew Tverdy - Light test fail on portion of the duct in the second floor chase
|
Rough-in | 8/31/2016 | 8/31/2016 | 8/31/2016 | A | PART |
Chad Schwendiman
|
|
|
Light test on grease duct 8:00am - Light test pass on 1 mitered piece
|
Rough-in | 8/26/2016 | 8/29/2016 | 8/29/2016 | P | PART |
Chad Schwendiman
|
|
|
Another partial light test for some offsets we are building. 2:00 p.m. would be good. Inspection requested via web by Drew Tverdy - light test pass on 3 miters
|
Rough-in | 8/24/2016 | 8/24/2016 | 8/24/2016 | P | PASS |
Chad Schwendiman
|
|
|
Partial light test for class 1 grease exhaust duct. 3:00 p.m. would be ideal. Phone #: ###-#### Inspection requested via web by Drew Tverdy - Grease duct light test pass on 6 each 12x12 striaght sections, and 2 each mitered pieces of 12x12
|