Final | 2/15/2018 | 2/16/2018 | 2/16/2018 | A | PASS |
Brian Scoles
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- final ok
|
Final | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Brian Scoles
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- temp occupancy ok- need to strap all gas piping supports on roof- need to hook up dryers when installed-
|
Final | 1/25/2018 | 1/26/2018 | 1/26/2018 | A | PART |
Brian Scoles
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER- cook line gas piping all good- water heater rooms for bldg 100 and 300 ok- need to finish dryer gas piping and look at bldg 300 water heater room was locked uo- need to walk roof- call in finl when all work is completed
|
Mec-Aging Inspection | 1/3/2018 | 1/3/2018 | 1/3/2018 | | CANC |
Brian Scoles
|
|
|
work in progress
|
Pressure Test | 10/4/2017 | 10/4/2017 | 10/4/2017 | A | PASS |
Alan Hauser
|
|
|
whole system 60#
|
Pressure Test | 10/2/2017 | 10/3/2017 | 10/3/2017 | A | PART |
Alan Hauser
|
|
|
60# test on all piping on roof
|
Pressure Test | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | PASS |
Ben Livingston
|
|
|
ROSS IS THE JOB CONTACT ###-#### Phone #: ###-#### Inspection requested via web by BECCA DUMMER 60 lb test mechanical room to roof pass 60lb test kitchen cook line pass
|
Mec-Aging Inspection | 6/16/2017 | 6/16/2017 | 6/16/2017 | | CANC |
Alan Hauser
|
|
|
|