Final | 5/19/2017 | 5/19/2017 | 5/19/2017 | P | PASS |
Chad Schwendiman
|
|
|
Max, ###-####. Thanks! Inspection requested via web by Floyd Floyd Peek
|
Rough-in | 3/15/2017 | 3/15/2017 | 3/15/2017 | A | PASS |
Brian Scoles
|
|
|
Inspection requested via web by Floyd Floyd Peek- 20 lb gas pass- 5lb flue pass- R/I ok
|
Rough-in | 3/14/2017 | 3/14/2017 | 3/14/2017 | A | FAIL |
Brian Scoles
|
|
|
Inspection requested via web by Floyd Floyd Peek- need r/a to bedroom 4 first floor- b vent need 1 inch clearance to combustibles and insulation shields level 1 at ceiling and level 2 chase and b vent secured- need flue press test- make up air to laundry room- went over with Max- correction notice front window
|
Pressure Test | 3/13/2017 | 3/13/2017 | 3/13/2017 | P | PART |
Chad Schwendiman
|
|
|
Max will call inspector when it''s ready, Max ###-#### Inspection requested via web by Floyd Floyd Peek - 20lb gas pass, flue not ran at this time
|
Rough-in | 3/13/2017 | 3/13/2017 | 3/13/2017 | P | FAIL |
Chad Schwendiman
|
|
|
Inspection requested via web by Floyd Floyd Peek - rough in not complete
|