Final | 10/12/2017 | 10/12/2017 | 10/12/2017 | P | PASS |
Brian Scoles
|
|
|
Field Super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney
|
Final | 10/10/2017 | 10/11/2017 | 10/11/2017 | P | FAIL |
Brian Scoles
|
|
|
Field Super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney- need duct blast completed to final permit out- left correction notice on furnace
|
Final | 10/6/2017 | 10/6/2017 | 10/6/2017 | P | PART |
Brian Scoles
|
|
|
Field super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney- need duct blast completed to final out
|
Rough-in | 8/17/2017 | 8/18/2017 | 8/18/2017 | A | PASS |
Brian Scoles
|
|
|
Field Super; Jason Shipp Phone #: ###-#### Inspection requested via web by Lisa Whitney
|
Rough-in | 8/17/2017 | 8/18/2017 | 8/17/2017 | P | CANC |
Brian Scoles
|
|
|
Field Super: Jason Shipp (re-inspect) Phone #: ###-#### >> Inspection requested via web by Lisa Whitney Inspection cancelled from web by: Lisa Whitney
|
Rough-in | 8/16/2017 | 8/17/2017 | 8/17/2017 | P | FAIL |
Brian Scoles
|
|
|
Field Super Jason Shipp Phone #: ###-#### Inspection requested via web by Lisa Whitney- need approved manual J onsite to do inspection- b vent needs 1" clearance to combustibles 2nd floor shaft at ceiling and possibly at roof penetration
|
Pressure Test | 8/16/2017 | 8/17/2017 | 8/17/2017 | P | PASS |
Brian Scoles
|
|
|
Field Super Jason Shipp Phone #: ###-#### Inspection requested via web by Lisa Whitney- 20lb gas pass- 5lb flue pass
|
Rough-in | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | NR |
Brian Scoles
|
|
|
field super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney
|
Pressure Test | 8/14/2017 | 8/15/2017 | 8/15/2017 | A | NR |
Brian Scoles
|
|
|
field super: Daryl Thomas Phone #: ###-#### Inspection requested via web by Lisa Whitney
|