Permit Information
Permit NumberMEC17-03517
StatusFinaled
Name ADVANCED HEATING & COOLING
Site Address 7655 N JENNIE LN
Project Name 
Customer Number 
ePlanReviewNo
Description
New: Supply and install 6) gas furnaces, 6) coils, 6) thermostats, 6) air conditioners, 6) motorized dampers, 1) Denlar hood, 6) exhaust fans, 6) filter racks, 5) electric hoods, balancing, duct work, grilles, registers, louvers, and termination kits.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final2/26/20182/26/20182/26/2018PPASS
DetailsChad Schwendiman
River Academy - final inspection requested.
Job lead is Chris Jacobson ###-#### Phone #: ###-#### Inspection requested via web by Jess Wigley
Final2/22/20182/23/20182/23/2018ACANC
DetailsBen Livingston
River Academy - final inspection requested.
Job lead is Chris Jacobson ###-#### Phone #: ###-#### >> Inspection requested via web by Jess Wigley Inspection cancelled from web by: Jess Wigley
Final1/29/20181/30/20181/30/2018ANR
DetailsBen Livingston
River Academy - Final fire wrap for the grease duct Phone #: ###-#### Inspection requested via web by Jess Wigley
Rough-in1/30/20181/30/20181/30/2018PPASS
DetailsBen Livingston
River Academy - Final fire wrap for the grease duct Phone #: ###-#### Inspection requested via web by Jess Wigley
fire wrap
Rough-in1/24/20181/25/20181/25/2018APASS
DetailsBen Livingston
River Academy - inspection requested for first layer of fire wrap on kitchen grease duct. Phone #: ###-#### Inspection requested via web by Jess Wigley
1st layer okay
Rough-in1/17/20181/18/20181/18/2018PPART
DetailsBen Livingston
River Academy light test requested for grease duct. Job lead is Casey Heesch ###-####, please contact if questions. Phone #: ###-#### Inspection requested via web by Jess Wigley
light test pass
Conference12/28/201712/28/201712/28/2017PFAIL
DetailsBen Livingston
Conference to discuss ERU location on rooftop in regards to condenser location. Call job lead, Chris Jacobson with any questions. ###-#### Phone #: ###-#### Inspection requested via web by Jess Wigley
access doors on ERU need to open all the way. moving the condencer looks to be easiest fix
Conference12/21/201712/22/201712/22/2017APASS
DetailsBen Livingston
Job lead: Chris Jacobson - consultation to discuss rooftop units Phone #: ###-#### Inspection requested via web by Jess Wigley
Rough-in11/29/201711/30/201711/30/2017APASS
DetailsBen Livingston
River Academy: Cover inspection requested for Chris Jacobson ###-#### Phone #: ###-#### Inspection requested via web by Jess Wigley
1st 2nd floor duct seal and hard lids okay
Conference10/3/201710/4/201710/4/2017PPASS
DetailsBen Livingston
Conference requested to discuss clearances and duct insulation. Job lead is Chris Jacobson ###-####
5lb flue x4 Phone #: ###-#### Inspection requested via web by Jess Wigley