Final | 12/21/2017 | 12/21/2017 | 12/21/2017 | A | PASS |
Brian Scoles
|
|
|
final ok- occupancy card signed
|
Final | 11/21/2017 | 11/21/2017 | 11/21/2017 | P | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- final ok- will final out after other mech permit has been inspected for TVR
|
Final | 11/13/2017 | 11/13/2017 | 11/13/2017 | P | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- 60lb gas pass whole system tested- need to have unit heater installed to final out- temp occupancy ok
|
Final | 10/10/2017 | 10/11/2017 | 10/11/2017 | A | PART |
Brian Scoles
|
|
|
Partial Final Phone #: ###-#### Inspection requested via web by Nicholas Paige- existing building furnace closet gas piping ok
|
Pressure Test | 9/13/2017 | 9/13/2017 | 9/13/2017 | P | PASS |
Ben Livingston
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige 60 lb test and piping from meter to mechanics shop
|