Mec-Aging Inspection | 7/27/2020 | 7/27/2020 | 7/27/2020 | | DONE |
Jack Reynolds
|
|
|
WIP Talked with contractor about plans for next phase. He says the owner is planning on starting work again after summer.
|
Mec-Aging Inspection | 4/27/2020 | 4/27/2020 | 4/27/2020 | | DONE |
Jack Reynolds
|
|
|
Corrections on guest room exhaust fans have been done under permit MEC20-00571
|
Conference | 1/27/2020 | 1/27/2020 | 1/27/2020 | A | DONE |
Chad Schwendiman
|
|
|
Sent out a letter from the City Attorney's office to the Owner, Archtect and the Hotel on Friday 1/24/2020
|
Conference | 1/6/2020 | 1/6/2020 | 1/6/2020 | P | DONE |
Chad Schwendiman
|
|
|
Followed up With Yuriy on status of exhaust fans for 2nd and 3rd floor guest rooms. He stated he still hasn't heard back from the genral contarctor since sending them a quote to fix them.
|
Mec-Aging Inspection | 10/22/2019 | 10/22/2019 | 10/22/2019 | | PASS |
Jack Reynolds
|
|
|
WIP
|
Mec-Aging Inspection | 7/23/2019 | 7/23/2019 | 7/23/2019 | | DONE |
Jack Reynolds
|
|
|
WIP
|
Mec-Aging Inspection | 4/23/2019 | 4/23/2019 | 4/23/2019 | | DONE |
Jack Reynolds
|
|
|
Called and talked with the hvac contractor about this mechanical aging permit. He said that he is waiting on the general contractor to move forward with some of the project. WIP
|
Mec-Aging Inspection | 1/22/2019 | 1/22/2019 | 1/22/2019 | | FAIL |
Jack Reynolds
|
|
|
need to scheduled inspection
|
Mec-Aging Inspection | 10/19/2018 | 10/19/2018 | 10/19/2018 | | CANC |
Jack Reynolds
|
|
|
|
Rough-in | 4/13/2018 | 4/13/2018 | 4/13/2018 | P | PASS |
Chad Schwendiman
|
|
|
check exaust fans in rooms 206,208,212,214,216. second floor (main lobby enterance) Inspection requested via web by yuriy kryachun
|
Rough-in | 4/1/2018 | 4/2/2018 | 4/2/2018 | A | PASS |
Chad Schwendiman
|
|
|
Prep room damper inspection Inspection requested via web by yuriy kryachun
|
Rough-in | 3/29/2018 | 3/30/2018 | 3/30/2018 | A | FAIL |
Chad Schwendiman
|
|
|
check fire damper in prep room. Phone #: ###-#### Inspection requested via web by yuriy kryachun - Need to remove all fire caulk from fire damper
|
Rough-in | 3/9/2018 | 3/9/2018 | 3/9/2018 | P | PART |
Chad Schwendiman
|
|
|
Kitchen prep area okay to cover ceiling, need to install a fire damper in duct where it penetrates the ceiling. will inspect once installed
|
Rough-in | 3/4/2018 | 3/5/2018 | 3/5/2018 | P | PART |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by yuriy kryachun - Okay to cover bathroom ceilings in rooms 136, 138, 140
|
Rough-in | 3/1/2018 | 3/2/2018 | 3/2/2018 | A | PART |
Chad Schwendiman
|
|
|
yurri Phone #: ###-#### - okay to cover bathroom ceilings in rooms 130-135, 137, 139, 141
|
Rough-in | 2/22/2018 | 2/23/2018 | 2/23/2018 | P | PART |
Chad Schwendiman
|
|
|
Yuriy Phone #: ###-#### - Okay to cover bathroom ceilings in rooms 430-440
|
Conference | 2/21/2018 | 2/22/2018 | 2/22/2018 | A | DONE |
Chad Schwendiman
|
|
|
Yuriy Phone #: ###-#### - Went over the installation of the exhaust fans in a soffit with Yuriy
|
Rough-in | 2/13/2018 | 2/14/2018 | 2/14/2018 | A | PART |
Chad Schwendiman
|
|
|
Yuri Phone #: ###-#### - Okay to cover bathroom ceilings in rooms 401-425
|
Rough-in | 2/5/2018 | 2/6/2018 | 2/6/2018 | A | PART |
Chad Schwendiman
|
|
|
Yuriy Phone #: ###-#### - bathroom ceilings okay in rooms 112-126
|
Conference | 2/1/2018 | 2/2/2018 | 2/2/2018 | A | DONE |
Chad Schwendiman
|
|
|
Yuri Phone #: ###-#### - Went by to look at the installation of a fan and ducting in one if the units. I let them know they still need to install sheetrock between the joists on the bottom side of the floor above per manufactures instructions
|