Final | 5/7/2018 | 5/7/2018 | 5/7/2018 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- final on 4 units ok
|
Final | 5/2/2018 | 5/3/2018 | 5/3/2018 | P | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak unti 101- lineset in mech room needs insulation,taped, and supported- indoor unit needs braced to wall/supported-need duct blast and air balance reports onsite unit 102- lineset in mech room needs insulated and supported- fresh air ducts need insulated- need duct blast and air balance reports onsite unit 103- lineset in mech room needs insulated and supported - lineset at outdoor unit needs UV protection- indoor unit needs to be braced to wall- need duct blast and air balance reports onsite unit 104- mech room was locked - need duct blast and air balance reports onsite
|
Final | 4/27/2018 | 4/27/2018 | 4/27/2018 | P | NR |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- work needs to be done not ready for final.
|
Rough-in | 1/29/2018 | 1/30/2018 | 1/30/2018 | P | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak
|