Final | 6/1/2018 | 6/1/2018 | 6/1/2018 | P | PASS |
Chad Schwendiman
|
|
|
Inspection requested via web by Floyd Floyd Peek
|
Rough-in | 3/19/2018 | 3/19/2018 | 3/19/2018 | P | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Floyd Floyd Peek
|
Pressure Test | 3/19/2018 | 3/19/2018 | 3/19/2018 | A | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Floyd Floyd Peek - 20lb gas, 5lb flue
|
Rough-in | 3/19/2018 | 3/19/2018 | 3/19/2018 | A | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Floyd Floyd Peek - need to complete sealing the return duct in mechanical shaft on 2nd floor, Need framing completed on mechanical shaft on 2nd floor and nail plates installed on PVC flue.
|