Final | 6/27/2018 | 6/27/2018 | 6/27/2018 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- final on all 6 units ok
|
Final | 6/26/2018 | 6/26/2018 | 6/26/2018 | P | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- need approved manual J onsite(leave in unit 106 kitchen drawer)- need to level unit number 101 102 and 103 condenser pads outside
|
Rough-in | 4/8/2018 | 4/9/2018 | 4/9/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- R/I ok
|
Rough-in | 4/5/2018 | 4/6/2018 | 4/6/2018 | P | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- need to insulare supply and R/A bare metal in attic- need approved hangers on lineset panduits dont work- need to resubmit man J with right brand installed
|
Rough-in | 4/5/2018 | 4/5/2018 | 4/5/2018 | A | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak- need approved manual j onsite for inspection-
|