Final | 7/11/2018 | 7/12/2018 | 7/12/2018 | A | PASS |
Jack Reynolds
|
|
|
AC: 2018 Phone #: ###-#### Inspection requested via web by Gary Reeves- final ok- linset supported ok - exhaust fan ok- range hood exhaust ok
|
Final | 7/10/2018 | 7/11/2018 | 7/11/2018 | A | FAIL |
Jack Reynolds
|
|
|
AC:2018 Phone #: ###-#### Inspection requested via web by Gary Reeves- No access to home and the lineset support at the outdoor unit was not finished yet
|
Final | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | NR |
Jack Reynolds
|
|
|
AC: 2018 Phone #: ###-#### Inspection requested via web by Gary Reeves- not ready still need exhaust fans, lineset supported, range exhaust, gasline to water heater
|
Final | 7/5/2018 | 7/6/2018 | 7/6/2018 | A | PART |
Jack Reynolds
|
|
|
duct blast witness at 9 am. thanks Phone #: ###-#### Inspection requested via web by Gary Reeves- ductblast ok- job still needs work finished for full final
|
Final | 7/4/2018 | 7/5/2018 | 7/5/2018 | A | NR |
Jack Reynolds
|
|
|
Ac 2018 Also need a duct blast witness Inspection requested via web by Gary Reeves- not ready for final- need exhaust fans in place- range hood installed- support lineset at outdoor unit- need air balance report onsite- ductblast wintness-
|
Rough-in | 4/26/2018 | 4/26/2018 | 4/26/2018 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves- duct seal ok- R/I ok
|
Rough-in | 4/24/2018 | 4/25/2018 | 4/25/2018 | P | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves- crawl space ok, framing around b vent is in place- still need to seal duct work inside the framing
|
Rough-in | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves- crawl space done, duct work sealed, still need to frame b vent
|
Pressure Test | 4/24/2018 | 4/24/2018 | 4/24/2018 | P | DONE |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves- pressure test was already passed
|
Rough-in | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | FAIL |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves - crawl not complete, need to seal metal duct work, need framing around B-vent
|
Pressure Test | 4/19/2018 | 4/19/2018 | 4/19/2018 | P | PASS |
Chad Schwendiman
|
|
|
Phone #: ###-#### Inspection requested via web by Gary Reeves - 20lb 5lb flue
|