Final | 9/4/2018 | 9/5/2018 | 9/5/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- final ok- card signed
|
Rough-in | 7/24/2018 | 7/24/2018 | 7/24/2018 | P | PASS |
Brian Scoles
|
|
|
please call 1 hr in advance Phone #: ###-#### Inspection requested via web by Nicholas Paige- seal on ducts ok- insulation ok- ok for ceiling tile to be installed
|
Rough-in | 7/20/2018 | 7/23/2018 | 7/23/2018 | A | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- no accress- no one onsite to let me in- called # listed twice no answer
|
Rough-in | 6/28/2018 | 6/29/2018 | 6/29/2018 | A | PART |
Brian Scoles
|
|
|
Cover inspection. call thad prior to arriving for access Phone #: ###-#### Inspection requested via web by Nicholas Paige- north end of builing seal ok- ok to insulate- will need inspection called in when roof curbs are installed and ducts connected and to check insulation- will need to pull tiles in other phase at final to verify that flex to registers is good tile was put in without and inspection
|
Rough-in | 4/26/2018 | 4/27/2018 | 4/27/2018 | A | PART |
Brian Scoles
|
|
|
2 more rooms Phone #: ###-#### Inspection requested via web by Nicholas Paige- SE corner and lobby seal and insulation ok- ok for grid- need to inspect registers when this is complete
|
Rough-in | 4/24/2018 | 4/25/2018 | 4/25/2018 | A | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- partial on phase 2 open area in center of building- duct sealing on lobby and SE corner offices ok, need to call for R/I when finished on SE corner and lobby
|
Rough-in | 4/10/2018 | 4/11/2018 | 4/11/2018 | A | PART |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Nicholas Paige- seal on duct off RTU 4 center of room ok- ok tominsulate this ducts only-
|