Final | 9/28/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Jack Reynolds
|
|
|
PLEASE CALL (APPRENTICE) JAMIE @ # LISTED BEFORE LEAVING FOR FINAL INSPECTION ON 4-5 TON ROOFTOP PACKAGE UNIT. Phone #: ###-#### Inspection requested via web by SOPHIA FLEMING -RTU final ok
|
Final | 9/25/2018 | 9/28/2018 | 9/28/2018 | P | FAIL |
Jack Reynolds
|
|
|
PLEASE CALL (APPRENTICE) JAMIE @ # LISTED WHEN EN ROUTE TO INSPECT ROOFTOP 4-5 TON COMMERCIAL PACKAGE UNIT. Phone #: ###-#### Inspection requested via web by SOPHIA FLEMING - rtu fuse size too big- condensate needs to be installed properly- need a gas shut off valve within 6 ft of unit
|
Final | 9/25/2018 | 9/28/2018 | 9/25/2018 | A | CANC |
Jack Reynolds
|
|
|
CALL TENANT JUDY @ # LISTED WHEN EN ROUTE. PLEASE COME BETWEEN 9-11 IF POSSIBLE. Phone #: ###-#### >> Inspection requested via web by SOPHIA FLEMING Inspection cancelled from web by: SOPHIA FLEMING
|