Mec-Aging Inspection | 1/29/2020 | 1/29/2020 | 1/29/2020 | | DONE |
Brian Scoles
|
|
|
|
DOC - Permit Expired | 1/29/2020 | 1/29/2020 | 1/29/2020 | A | PASS |
Brian Scoles
|
|
|
no calls for inspection- multiple aging- permit expired
|
Mec-Aging Inspection | 10/30/2019 | 10/30/2019 | 10/30/2019 | | CANC |
Brian Scoles
|
|
|
no calls- no activity- bld still open- contractor needs to schedule final
|
Mec-Aging Inspection | 7/31/2019 | 7/31/2019 | 7/31/2019 | | FAIL |
Brian Scoles
|
|
|
contractor needs to call in final inspection if works complete- bld still open
|
Mec-Aging Inspection | 5/1/2019 | 5/1/2019 | 5/1/2019 | | FAIL |
Brian Scoles
|
|
|
needs final inspection called in by contractor no activity for 180 days- permit will expire next aging if no activity
|
Pressure Test | 9/12/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer- 60lb gas test pass underground from meter to bbq and pool heater- call in final when regulators are installed and works completed- ok to backfill
|
Pressure Test | 9/11/2018 | 9/11/2018 | 9/11/2018 | A | NR |
Brian Scoles
|
|
|
pool person onsite saying riser in wrong location at pump house- recall in inspection and retest system when issue resolved
|
Pressure Test | 9/10/2018 | 9/10/2018 | 9/10/2018 | P | FAIL |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Bryan Palmer- need to use approved material in underground gas piping- retest when completed with approved material- will need yellow tracer wire to all above ground connection missing at bbq
|