Final | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Jack Reynolds
|
|
|
PLEASE CALL STAN THE PROPERTY MANAGER WHEN 30 MINS IN ROUTE Phone #: ###-#### Inspection requested via web by Rick Montgomery - final ok - no card onsite to sign
|
Final | 10/25/2018 | 10/26/2018 | 10/26/2018 | P | CANC |
Jack Reynolds
|
|
|
please call Alex one of our technicians 30-40 mins ahead so he can meet you onsite for witnessed test. If at all possible, can this be end of day, 3-5p type time frame? If at all possible this would be appreciated, that way I can have the correct person there to meet you and have this all taken care of. Any questions or problems, call Steve at Diamond- ###-#### Phone #: ###-#### Inspection requested via web by Rick Montgomery
|
Rough-in | 10/26/2018 | 10/26/2018 | 10/26/2018 | P | PASS |
Jack Reynolds
|
|
|
please call Alex one of our technicians 30-40 mins ahead so he can meet you onsite for witnessed test. If at all possible, can this be end of day, 3-5p type time frame? If at all possible this would be appreciated, that way I can have the correct person there to meet you and have this all taken care of. Any questions or problems, call Steve at Diamond- ###-#### Phone #: ###-#### Inspection requested via web by Rick Montgomery -R/I ok smoke detectors installed per manuf spec and tested- ok for finish cover- will need to see access doors installed and trim finished for final
|
Final | 10/24/2018 | 10/25/2018 | 10/25/2018 | A | CANC |
Jack Reynolds
|
|
|
PLEASE CALL SAM OUR LEAD WHEN 30-45 MINS OUT SO HE CAN MEET YOU ONSITE AND PERFORM WITNESSED TEST Phone #: ###-#### >> Inspection requested via web by Rick Montgomery Inspection cancelled from web by: Rick Montgomery
|
Rough-in | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PART |
Jack Reynolds
|
|
|
Talked with Zach today about getting a partial R/I for cover so they can move foward with sheet rock. Zach said they would leave the ceiling open around the hvac units so that diamond havc can access the smoke detectors for testing and re mounting- Talked with Dave the building inspector and he said he was fine with a partial on the mechanical permit
|
Pressure Test | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | NR |
Jack Reynolds
|
|
|
please call Owen 30-40 mins when out so he can meet you onsite to perform test needed for you to witness. Phone #: ###-#### Inspection requested via web by Rick Montgomery- pressure differentional at smoke detector fail - talking with Owen they are going to try mounting the smoke detectors on the outside of the duct and apply the proper sampling tube and retest pressure- manufactures spec states a pressure differential of at least .01 - 1.2
|
Conference | 9/27/2018 | 9/27/2018 | 9/27/2018 | P | DONE |
Jack Reynolds
|
|
|
smoke detector installation- talked with general about leaving the smoke detector in place and testing air requirments through the smoke detectors to make sure they meet manufactures specs
|
Rough-in | 9/24/2018 | 9/25/2018 | 9/25/2018 | P | FAIL |
Jack Reynolds
|
|
|
Call Stan prior to going by there ###-#### - Need to provide test evidence that there enough air flow across the smoke detector in it current postion or install the smoke detector in a conventional way on the outside of the duct work so the sample tubes are in the air stream. You will also have to install fire rated access doors in the ceiling next to the smoke detectors
|
Rough-in | 9/24/2018 | 9/24/2018 | 9/24/2018 | A | CANC |
Jack Reynolds
|
|
|
Call Stan prior to going by there ###-#### Chad S.
|
Final | 9/11/2018 | 9/12/2018 | 9/12/2018 | A | PASS |
Jack Reynolds
|
|
|
PLEASE CALL ZACH THE PROJECT MANAGER WHEN 30 MINS IN ROUTE Phone #: ###-#### Inspection requested via web by Rick Montgomery- all fusible link dampers ok- 2 smoke detectors ok- ok for cover
|