Final | 5/23/2019 | 5/23/2019 | 5/23/2019 | P | PASS |
Jack Reynolds
|
|
|
Call for access- Office number. Phone #: ###-#### - final ok
|
Mec-Aging Inspection | 5/14/2019 | 5/14/2019 | 5/14/2019 | | DONE |
Jack Reynolds
|
|
|
WIP - talked with office on what needs to be done on this new construction site mainly the city needs to witness a duct blast test and perform a final inspection
|
Rough-in | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Jack Reynolds
|
|
|
kitchen toekick is part of the fantech system for crawl // Terek Phone #: ###-####- R/I ok
|
Pressure Test | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Jack Reynolds
|
|
|
Terek Phone #: ###-####- 5lb flue pressure test ok
|
Rough-in | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | FAIL |
Jack Reynolds
|
|
|
Terek Phone #: ###-#### - need city approved Man J stamped and onsite - toe kick in kitcken needs ran out from under kitcken cabinet -5lb flue pressure test fail - supply trunk going upstairs has a kink at a 90 degree turn that needs fixed
|
Pressure Test | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PART |
Jack Reynolds
|
|
|
Terek Phone #: ###-####- 5lb flue pressure test fail gauge was under 5lb- 20lb gas pressure test ok
|