Final | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PASS |
Chad Schwendiman
|
|
|
Thanks! Inspection requested via web by Floyd Floyd Peek
|
Rough-in | 12/4/2018 | 12/4/2018 | 12/4/2018 | P | FAIL |
Chad Schwendiman
|
|
|
South side needs ok to cover Inspection requested via web by Floyd Floyd Peek - Grills not hooked up or missing
|
Rough-in | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PART |
Ben Livingston
|
|
|
Need ok to cover lay-in ceiling area Inspection requested via web by Floyd Floyd Peek not all grid is done
|
Rough-in | 10/30/2018 | 10/30/2018 | 10/30/2018 | P | PASS |
Chad Schwendiman
|
|
|
Ready anytime. Partial for hard lid area, access is framed in. Thanks! Inspection requested via web by Floyd Floyd Peek - Okay to cover hard lids
|
Rough-in | 10/29/2018 | 10/29/2018 | 10/29/2018 | A | FAIL |
Chad Schwendiman
|
|
|
Partial Rough-in for hard ceiling area, Equipment was relocated into lay-in ceiling area. Inspection requested via web by Floyd Floyd Peek - There is still a exhaust fan installed above the hard lid
|
Rough-in | 10/24/2018 | 10/24/2018 | 10/24/2018 | P | FAIL |
Chad Schwendiman
|
|
|
Need partial R-I for hard lid area for cover. Inspection requested via web by Floyd Floyd Peek - Need access doors large enough for the removal of the equipment above hard lids framed in.
|