Final | 12/4/2018 | 12/4/2018 | 12/4/2018 | P | PASS |
Brian Scoles
|
|
|
Duct is insulated and sealed. Should be good. Phone #: ###-#### Inspection requested via web by Drew Tverdy- final ok- airbalance ok-
|
Final | 11/29/2018 | 11/30/2018 | 11/30/2018 | A | PART |
Brian Scoles
|
|
|
I will email balance report. call me with questions. Phone #: ###-#### Inspection requested via web by Drew Tverdy- need to seal and insulate MAU ducting in kitchen- need equipment set and in place- roof equipment ok- air balance ok-
|
Rough-in | 11/5/2018 | 11/5/2018 | 11/5/2018 | A | PASS |
Brian Scoles
|
|
|
I''ll be there at 8:30. Inspection requested via web by Drew Tverdy- 2nd layer fire wrap ok- make up duct seal ok- ok to cover
|
Rough-in | 11/2/2018 | 11/2/2018 | 11/2/2018 | A | PASS |
Brian Scoles
|
|
|
Light test and dish hood rough in. Will be ready by 9:30. Inspection requested via web by Drew Tverdy- light test on class 1 hood ok- class 2 hood seal ok-
|
Rough-in | 11/1/2018 | 11/1/2018 | 11/1/2018 | A | PASS |
Brian Scoles
|
|
|
Light test for 7 feet of duct. Will be ready by 10:30 Phone #: ###-#### Inspection requested via web by Drew Tverdy- light test pass on 7 feet
|