Final | 9/11/2019 | 9/16/2019 | 9/16/2019 | P | PASS |
Chad Schwendiman
|
|
|
Please call/text 20+ min before arrival. Thanks! ~Quinn Phone #: ###-#### Inspection requested via web by Quinn Anderson
|
Pressure Test | 8/25/2019 | 8/26/2019 | 8/26/2019 | A | PASS |
Chad Schwendiman
|
|
|
Please call/text 20 min before arrival. Thanks! Phone #: ###-#### Inspection requested via web by Quinn Anderson - 20lb gas pass
|
Mec-Request for Extension | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PASS |
Jack Reynolds
|
|
|
Call or text within 20 minutes /// Quinn Phone #: ###-#### - Talked with Quinn about the gas lines being installed. He stated he is getting close to having a pressure test ready. Quinn also stated he had issues with getting the pressure test to hold and that the pressure was bleeding off the meter regulator. I informed Quinn that he needed to keep the pressure test seperate from the meter. I called Clark with Intermountain Gas and informed them of the situation aswell.
|
Conference | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | DONE |
Jack Reynolds
|
|
|
Please call/text at least 30 min prior to arrival. Thanks! Phone #: ###-#### Inspection requested via web by Quinn Anderson
|
Conference | 1/21/2019 | 1/25/2019 | 1/25/2019 | P | NH |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Quinn Anderson - no access to home left notice
|