Final | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - final ok occ card signed
|
Final | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | PART |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - unit 100 needs condensate finished - three A/C's on north need to be level - air balances ok - dryer length stickers ok
|
Final | 5/10/2019 | 5/10/2019 | 5/10/2019 | P | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by Oleg Chervak - dryer labels/ tags need to be installed within 6' of dryer - west side line sets need more UV protection installed - some A/C's arent level and need to be fixed - need air balance reports on all units
|
Rough-in | 1/15/2019 | 1/16/2019 | 1/16/2019 | A | PASS |
Jack Reynolds
|
|
|
12 UNIT Phone #: ###-#### Inspection requested via web by Oleg Chervak - R/I on 12 units south side ok
|
Rough-in | 1/15/2019 | 1/15/2019 | 1/15/2019 | P | FAIL |
Jack Reynolds
|
|
|
12 units on south side of bld c
- units on each floor need duct seal and flex installed per manufacturers specs - this inspection was called in this afternoon under the wrong mech permit which was building A
|
Rough-in | 12/28/2018 | 12/28/2018 | 12/28/2018 | P | PART |
Jack Reynolds
|
|
|
n side unit 6 ea Phone #: ###-#### Inspection requested via web by Oleg Chervak - 6 units on the north side center of building duct R/I duct seal ok
|
Rough-in | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PART |
Jack Reynolds
|
|
|
PART 6 UNITS Phone #: ###-#### Inspection requested via web by Oleg Chervak - partial R/I on duct work for bld C northside 6 units only
|
Rough-in | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PART |
Jack Reynolds
|
|
|
MEC 18 UNITS BL C Phone #: ###-#### Inspection requested via web by Oleg Chervak - partial R/I for pre rock cover ok
|
Rough-in | 11/26/2018 | 11/27/2018 | 11/27/2018 | A | FAIL |
Jack Reynolds
|
|
|
PARTIAL Phone #: ###-#### Inspection requested via web by Oleg Chervak - need support on all line sets- some exhaust ducts need sealed- i want to see firecaulk on all hvac penetrations just a few locations needed caulk mainly locations behind furnaces in middle units - need to see a few nail plates installed - talked with alley hvac about labeling each permit with the building letter because last inspection was for the wrong building
|
Rough-in | 11/27/2018 | 11/27/2018 | 11/27/2018 | A | PART |
Jack Reynolds
|
|
|
PARTIAL Phone #: ###-#### Inspection requested via web by Oleg Chervak -building C north side exhaust ducts ok- ok for 1st layer cover- more R/I inspections to come when furnace duct work is installed
|