Final | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Jack Reynolds
|
|
|
David Phone #: ###-#### - final ok
|
Rough-in | 4/1/2019 | 4/1/2019 | 4/1/2019 | P | PASS |
Jack Reynolds
|
|
|
David Phone #: ###-####
|
Rough-in | 3/15/2019 | 3/18/2019 | 3/18/2019 | P | FAIL |
Jack Reynolds
|
|
|
David Phone #: ###-#### - b vent clearances through roof need to be 1" - owner decided to leave water heater in current location. But i still need to see framing installed around b vent so i can check clearances
|
Final | 3/15/2019 | 3/18/2019 | 3/18/2019 | P | CANC |
Jack Reynolds
|
|
|
David Phone #: ###-#### - not ready
|
Final | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | FAIL |
Jack Reynolds
|
|
|
Phone #: ###-#### - furnace flue needs 1" clearanes -flue needs insulation sheild in attic - duct work needs supported in crawl - need add gas line and duct work to permit - water heater closet next to furnace needs to framed and will have to be air tight on bedroom side so combustion is taken from outdoors/ access door needs to be self closing and sealed with weatherstripping - next inspection needs to be a R/I not a final - house looks to be in the process of being remodeled
|
Pressure Test | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### - 20lb gas pressure test ok -tagged gas meter
|