Final | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | PASS |
Brian Scoles
|
|
|
Please call Brad at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum- final ok
|
Final | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PART |
Brian Scoles
|
|
|
Please call Brad at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum- need all equipment installed under class 1 hood and dishwasher hood and side panels installed- need air balance report on both hoods- rest is good
|
Rough-in | 7/23/2019 | 7/24/2019 | 7/24/2019 | A | PASS |
Brian Scoles
|
|
|
Please call Brad at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum- R/I ok- ok for ceiling tiles- need air balance report for mau and class 1 hood at final and all equipment set into working place under class 1 hood
|
Rough-in | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | PASS |
Brian Scoles
|
|
|
Please call Brad at least 30 min prior to inspection, thank you. Phone #: ###-#### Inspection requested via web by Rhonda Marcum- grease duct light test pass- ok for first and second layer firewrap- ok for ceiling grid to install all areas-
|
Rough-in | 6/12/2019 | 6/12/2019 | 6/12/2019 | A | PASS |
Brian Scoles
|
|
|
all ducting seal ok- ok to insulate- need to see class 1 and 2 hoods still
|
Rough-in | 5/8/2019 | 5/8/2019 | 5/8/2019 | A | PART |
Brian Scoles
|
|
|
seal on ducts supply and exhaust ok- hardlids in bathrooms ok to cover only
|