Permit Information
Permit NumberMEC19-02272
StatusFinaled
Name PAIGE MECHANICAL GROUP INC
Site Address 5103 W BETHEL ST Unit: 110
Project Name 
Customer Number18.7245.23
ePlanReviewNo
Description
New: Install HVAC Equipment, trim, duct, controls, & Insulation
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final10/1/201910/3/201910/3/2019APASS
DetailsJack Reynolds
please call john 30 min prior to arriving so he can meet you onsite
thanks
Phone #: ###-#### Inspection requested via web by Nicholas Paige
- final ok
signed occ card
- talked with John about pulling a seperate mech permit for the shell gas piping and two unit heaters
Pressure Test6/26/20196/28/20196/28/2019APASS
DetailsJack Reynolds
Phone #: ###-#### Inspection requested via web by Nicholas Paige
2- 100lb gas pressure tests for building shell ok
1- 100lb gas pressure test for unit 110 ok
- tagged meter location
Pressure Test6/25/20196/26/20196/26/2019AFAIL
DetailsJack Reynolds
Phone #: ###-#### Inspection requested via web by Nicholas Paige
- high pressure test needs to be on 100lb gauge
- gas piping penetration needs protective coating
Rough-in6/12/20196/13/20196/13/2019APART
DetailsJack Reynolds
Phone #: ###-#### Inspection requested via web by Nicholas Paige
- R/I partial for lid cover ok
Rough-in6/12/20196/12/20196/12/2019AFAIL
DetailsJack Reynolds
Cover inspection
Phone #: ###-#### Inspection requested via web by Nicholas Paige
- need City approved prints onsite