Permit Information
Permit NumberMEC19-02852
StatusFinaled
Name TRANE
Site Address 412 E PARKCENTER BLVD Unit: STE 100
Project NameHDR TI
Customer Number19-8074875
ePlanReviewNo
Description
Alteration: Ductwork modification and relocating existing heat pump
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final9/26/20199/27/20199/27/2019PPASS
DetailsJack Reynolds
This is a rough-in final. Final inspection for project will be scheduled after air balance which will be next week. Call Glen with any questions. Phone #: ###-#### Inspection requested via web by Yvonne Bowman
- final ok
Rough-in9/25/20199/26/20199/26/2019PPASS
DetailsJack Reynolds
This inspection is for "cover" requested time would be after 3PM if possible. Call Glen with any questions ###-#### Phone #: ###-#### Inspection requested via web by Yvonne Bowman
- duct seal on three duct runs ok for insulation cover
Rough-in8/27/20198/28/20198/28/2019PPASS
DetailsJack Reynolds
This is for a "to cover" inspection. Please call Glen with any issues ###-#### Phone #: ###-#### Inspection requested via web by Yvonne Bowman
- R/I insulation ok
- Cover ok phase 4
Rough-in8/26/20198/27/20198/27/2019PPART
DetailsJack Reynolds
This is a rough-in for Phase 4 of the project. Please call Glen with any questions. Thank you. Phone #: ###-#### Inspection requested via web by Yvonne Bowman
- phase 4 partial R/I ok duct seal ok
- ok for insulation cover
Final8/12/20198/12/20198/12/2019PPART
DetailsJack Reynolds
this is a "partial final" inspection. No one from Trane will be onsite so please call with any questions. Thank you. Phone #: ###-#### Inspection requested via web by Crystal Grant
- phase 1 parial final ok will receive full final when the rest of the remodel is finished
Rough-in7/18/20197/19/20197/19/2019APASS
DetailsJack Reynolds
Please contact Glen at ###-#### if needed. Phone #: ###-#### Inspection requested via web by Crystal Grant
- R/I cover of ceiling phase 1 ok
Rough-in7/12/20197/15/20197/15/2019APART
DetailsJack Reynolds
Call ahead // Mike Phone #: ###-####
- partial R/I ok
- duct seal in phase 1 open office area ok for insulation cover
- contractor still needs to run one 8" supply branch into hallway