Final | 3/27/2020 | 3/30/2020 | 3/30/2020 | A | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by yuriy kryachun - final on shell and core ok
|
Final | 3/24/2020 | 3/25/2020 | 3/25/2020 | A | FAIL |
Jack Reynolds
|
|
|
Inspection requested via web by yuriy kryachun - line sets need UV protection - A/C needs locking caps - regulator need test ports installed downstream and up stream - arma flex insulation at indoor units need repaired - protection posts need installed at A/C's
|
Mec-Aging Inspection | 3/17/2020 | 3/17/2020 | 3/17/2020 | | PASS |
Jack Reynolds
|
|
|
WIP
|
Pressure Test | 12/17/2019 | 12/18/2019 | 12/18/2019 | A | PASS |
Jack Reynolds
|
|
|
Gas lines straped up and under pressure Inspection requested via web by yuriy kryachun 2- 20lb gas pressure test ok tagged meter locations
|
Pressure Test | 12/16/2019 | 12/17/2019 | 12/17/2019 | P | FAIL |
Jack Reynolds
|
|
|
Need another gas pressure test as the project changed to two gaslines Inspection requested via web by yuriy kryachun - This permit is for shell and core only. If 1st floor is being built out then a new permit is required. The 1st floor build out will also need to be reviewed by the City of Boise and a stamped set of prints onsite for inspection - both gas lines outside need supported to wall
|
Rough-in | 8/11/2019 | 8/12/2019 | 8/12/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by yuriy kryachun - R/I ok - plumbing vent going through roof needs to be extended 3' above fresh air on unit downstairs - contractor will pipe out combustion air for both furnaces for final - -
|
Pressure Test | 8/11/2019 | 8/12/2019 | 8/12/2019 | P | PASS |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by yuriy kryachun 2- 5lb flue pressure tests ok -20lb gas pressure test ok - tagged meter location
|
Conference | 7/4/2019 | 7/5/2019 | 7/5/2019 | A | DONE |
Jack Reynolds
|
|
|
Phone #: ###-#### Inspection requested via web by yuriy kryachun
|