Final | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Jack Reynolds
|
|
|
final Phone #: ###-#### Inspection requested via web by Brandon Sorensen - final ok - occ card signed
|
Final | 9/5/2019 | 9/6/2019 | 9/6/2019 | A | FAIL |
Brian Scoles
|
|
|
final - call Phone #: ###-#### Inspection requested via web by Brandon Sorensen- no access all locked up
|
Final | 8/20/2019 | 8/21/2019 | 8/21/2019 | A | PART |
Brian Scoles
|
|
|
final Phone #: ###-#### Inspection requested via web by Brandon Sorensen- ok to install ceiling tiles- per conversation with GC start up needs completed- recall in when ready
|
Rough-in | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | PASS |
Brian Scoles
|
|
|
cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen- remaining seal on ducts ok- ok to insulate- leave ceiling tiles out at drops to see insulation at final- need access to roof at final for RTU
|
Rough-in | 7/9/2019 | 7/10/2019 | 7/10/2019 | A | PASS |
Brian Scoles
|
|
|
cover Phone #: ###-#### Inspection requested via web by Brandon Sorensen- seal on supply, exhaust and return ok- ok to insulate- need to look at drops from unit once installed- call in when ready
|