Final | 10/31/2019 | 10/31/2019 | 10/31/2019 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Konrad Swartz- final ok- locking caps installed on a/c
|
Final | 10/29/2019 | 10/30/2019 | 10/30/2019 | A | FAIL |
Brian Scoles
|
|
|
Back door is open Phone #: ###-#### Inspection requested via web by Konrad Swartz- need locking caps on a/c service ports- rest is good
|
Conference | 10/2/2019 | 10/2/2019 | 10/2/2019 | A | PASS |
Brian Scoles
|
|
|
duct blast test 830am- duct blast test pass
|
Rough-in | 8/26/2019 | 8/26/2019 | 8/26/2019 | P | PASS |
Brian Scoles
|
|
|
Phone #: ###-#### Inspection requested via web by Konrad Swartz- R/I ok
|
Rough-in | 8/19/2019 | 8/19/2019 | 8/19/2019 | P | PART |
Brian Scoles
|
|
|
Inspection requested via web by Konrad Swartz- seal on ducts both floors ok- ok to insulate duct in attic- recall in r/i inspection when complete and insulation has been installed in attic
|