Final | 9/20/2019 | 9/23/2019 | 9/23/2019 | A | PASS |
Jack Reynolds
|
|
|
Izzy Phone #: ###-#### - final ok - will sign occ card when 2nd mechanical permit passes final
|
Rough-in | 9/17/2019 | 9/18/2019 | 9/18/2019 | A | PASS |
Jack Reynolds
|
|
|
Izzy Phone #: ###-#### - R/I ok
|
Rough-in | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | FAIL |
Jack Reynolds
|
|
|
Call for code // Izzy Phone #: ###-#### - b vent for unit heaters needs 1" clearances to combustibles - paint booth exhaust duct has a seam that needs sealed
|
Rough-in | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | NR |
Jack Reynolds
|
|
|
IZZIE- PLEASE CALL FOR ACCESS PRIOR 30MIN Phone #: ###-#### - not ready contractor still needs to deal with exhaust duct clearances of 6" to combustibles
|
Rough-in | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | FAIL |
Jack Reynolds
|
|
|
Izzy-wants a call 30 minutes prior to meet for access Phone #: ###-#### - no access to building called Izzy ahead of time and left voicemail
|
Final | 8/30/2019 | 8/30/2019 | 8/30/2019 | P | FAIL |
Jack Reynolds
|
|
|
call for lockbox code if necessary // Izzy Phone #: ###-#### - need to see clearances on unit heater flues and paint booth exhaust duct - unit heater needs 18" service clearances - unit heaters need a concentric kit or two pipe system for combustion - flues on roof need supported - seismic bracing of unit heaters - this should have been a R/I inpsection - will need to see balance report of system for final
|
Pressure Test | 8/30/2019 | 8/30/2019 | 8/30/2019 | P | PASS |
Jack Reynolds
|
|
|
call for lockbox code if necessary // Izzy Phone #: ###-#### - 60 lb gas pressure test ok - tagged meter location
|