Final | 12/16/2019 | 12/16/2019 | 12/16/2019 | A | PASS |
Jack Reynolds
|
|
|
- corrections on 104 and 105 Area A ok - 8 fireplaces Area A final ok
|
Rough-in | 8/19/2019 | 8/20/2019 | 8/20/2019 | P | PASS |
Jack Reynolds
|
|
|
103K, 104P, 105P, 106Q, 203K, 204P, 205V, 302S. PLEASE CALL SHELDON 1 HOUR BEFORE ARRIVAL. ###-#### Phone #: ###-#### Inspection requested via web by Sheldon Lebow - units 103,104,105,106,203,204,205,302 fireplace R/I ok
|
Rough-in | 8/9/2019 | 8/9/2019 | 8/9/2019 | P | FAIL |
Jack Reynolds
|
|
|
UNITS 103K, 104P,105P,106Q,203K,204P,205V,302S Phone #: ###-#### Inspection requested via web by Sheldon Lebow - all fireplaces need secured to framing - all fireplaces need saw dust/ buidling materials cleaned off top of fireplace - all fireplaces need romex wiring on back of fireplace secured so fireplace has 1/2 clearances on back -106 needs firestop/ venting installed properly as to acheive 3" clearances on top of venting to required frame out in wall
|
Rough-in | 7/31/2019 | 8/1/2019 | 7/31/2019 | A | CANC |
Jack Reynolds
|
|
|
UNIT 106Q Phone #: ###-#### >> Inspection requested via web by Sheldon Lebow Inspection cancelled from web by: Sheldon Lebow
|
Rough-in | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | CANC |
Jack Reynolds
|
|
|
PLEASE CALL SHELDON ON THE WAY OVER TO THE PROJECT ###-#### Phone #: ###-#### Inspection requested via web by Sheldon Lebow - I talked with Sheldon and he is going to talk with the general contractor, button up a few things and reschedule at a later date
|
Rough-in | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | FAIL |
Jack Reynolds
|
|
|
UNITS 103K, 104P, 105P, 106Q, 203K, 204P, 205V, 302S Phone #: ###-#### Inspection requested via web by Sheldon Lebow - all unit listed above need framing done, installation instructions at each fireplace, electrical wiring and conduit is touching fireplace venting 106Q also needs venting to slope
|