Card not on site to sign | 8/8/2019 | 8/8/2019 | 8/8/2019 | P | PASS |
Jack Reynolds
|
|
|
ok
|
Final | 8/8/2019 | 8/8/2019 | 8/8/2019 | P | PASS |
Jack Reynolds
|
|
|
Jason Davidson site contact. TAB report to follow. Phone #: ###-#### Inspection requested via web by RM Mechanical - final ok
|
Final | 7/30/2019 | 7/31/2019 | 7/31/2019 | A | CANC |
Jack Reynolds
|
|
|
Rough in / final inspection. Jason Davidson site contact. Phone #: ###-#### Inspection requested via web by RM Mechanical - will need to see balance report on paint booth for final
|
Rough-in | 7/31/2019 | 7/31/2019 | 7/31/2019 | A | FAIL |
Jack Reynolds
|
|
|
Rough in / final inspection. Jason Davidson site contact. Phone #: ###-#### Inspection requested via web by RM Mechanical - need to see all duct joints sealed on make up air and exhaust ducts - talked with General about a deleted RAL on west wall. He is going to get me docs showing the approval of opening being deleted. - once paint booth is up and running will need to see balance report for final
|