Final | 9/12/2019 | 9/12/2019 | 9/12/2019 | P | PASS |
Ben Livingston
|
|
|
|
Rough-in | 8/8/2019 | 8/12/2019 | 8/12/2019 | A | PASS |
Ben Livingston
|
|
|
second layer fire wrap inspection. Phone #: ###-#### Inspection requested via web by Drew Tverdy
|
Rough-in | 8/1/2019 | 8/1/2019 | 8/1/2019 | P | PASS |
Ben Livingston
|
|
|
Light test on 2 remaining seams. Mid afternoon Phone #: ###-#### Inspection requested via web by Drew Tverdy -- 2 tie in welds light test, 1st layer fire wrap--
|
Rough-in | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | PASS |
Ben Livingston
|
|
|
light test on partial grease duct so we can wrap and put in place. will be ready by 10:00 Phone #: ###-#### Inspection requested via web by Drew Tverdy -- 2 sections of grease duct both with elbows light test--
|