Final | 9/11/2019 | 9/11/2019 | 9/11/2019 | P | PASS |
Jack Reynolds
|
|
|
Restroom remodel. The laundry closet will not have a door. The backdoor will be open for access to inspect the house Phone #: ###-#### Inspection requested via web by Nicolas Barajas - final ok
|
Rough-in | 8/19/2019 | 8/20/2019 | 8/20/2019 | A | PASS |
Jack Reynolds
|
|
|
Re-inspection. Smashed dryer vent was replaced. Builder is going to make the dryer wall 2x6. Make up air for laundry room will be installed at the door. Key to gain access is in the back at the power meter. Phone #: ###-#### Inspection requested via web by Nicolas Barajas - R/I ok - check make air for laundry closet at final
|
Rough-in | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | FAIL |
Jack Reynolds
|
|
|
Key is on top of the Idaho power meter located by the back door. House is empty Phone #: ###-#### Inspection requested via web by Nicolas Barajas - dryer vent is being smashed. Vent should be installed in a 2x6 wall or furred out to make room for vent - need to see a transfer into laundry closet
|